twitter facebook linkedin

More than 35 years
of experience in Texas

previous arrow
next arrow
Slider

Northwinds Construction

View important updates by Northwinds Construction

Closner Equipment

Closner Equipment | 20,993 SF Office, Repair Shop, and Washbay | Elgin, TX

12.12.24 - The foundation is poured and is curing,

12.12.24

 

12.09.24 - Crews are forming for the foundation pour,

12.09.24

12.05.24 - Crews are pouring piers,

12.05.24

 

10.23.24 - Site crewmen are bringing in fill for the pad,

IMG 2024 10 23 08 26 05 969 copy

IMG 2024 10 23 15 01 00 990 copy

 

10.22.23 - Crewmen continue excavation for the pad,

IMG 2024 10 22 16 13 14 420 copy

 

10.17.24 - Dirt crew started mass grading and excavation for the pad. They will start building the pads for the foundation next week,

IMG 8225 copy

IMG 8226 copy

IMG 8227 copy

IMG 8228 copy

IMG 8229 copy

 

9.23.24 - We participated in a ground breaking ceremnony for Closner Equipment. Closner Equipment is a repeat client of Northwinds. We completed their Waller facility in 2023. Closner is a heavy equipment dealer/repair facility that specializes in road work. Closer has selected Northwinds to design and construction their new facility in Elgin, TX. The facility will be built on a six acre tract located on the US 290 frontage. The improvements include 20,993 SF of buildings to include an office, repair shop, and wash bay. The site work will include asphalt, concrete, and a large rock yard.

20240923 104748

20240923 104827

20240923 104851

20240923 104941

20240923 105007

20240923 105054

 

 

  662 Hits
662 Hits

HTeaO

HTeaO | 2,249 SF | Klein, TX

This project includes a 1,109 SF kitchen, a 1,029 SF mercantile, and 112 SF of storage.

12.12.24 - MEP, interior wall, interior ceiling, and Millwork continue. The drives are poured and the drivethrough equipment installation is underway,

12.12.24

12.12.24 7

12.12.24 6

12.12.24 2

12.12.24 3

12.12.24 4

12.12.24 5

 

11.26.24 - Millwork and MEP work continue. Canopies and the trash gates are installed,

11.26.24 3

11.26.24 4

11.26.24 2

11.26.24

10.25.24 - Electrical and HVAC continue. Crews are taping and floating the interior. Exterior canopy and light installation are underway,

10.25.24

10.25.24 3

10.25.24 2

10.25.24 4

10.25.24 5

10.25.24 6

 

10.16.24 - Interior drywall continues. Additional driveways were poured,

10.16.24 3

10.16.24

10.16.24 2

 

10.10.24 - Electrical and HVAC continue,

10.10.24

10.10.24 2

10.01.24 - Masonry work is underway. Interior electrical and buildout continues,

10.01.24

10.01.24 2

9.24.24 - Doors and windows are installed. Electrical is underway,

9.24.24

9.24.24 2

9.24.24 3

9.18.24 -

9.18.24

9.04.24 - Crews are framing the building,

9.04.24

8.06.24 - Framing for a  pavement pour,

8.06.24

8.02.24 - Crewmen are pouring the building foundation this morning,

8.02.24 2

8.02.24

 

6.04.24 - Storm and utility work continue,

6.04.24

5.10.24 - Storm and utility work are underway,

5.23.24 2

5.23.24

 

4.17.24 - Sitework continues,

4.17.24 2

 

4.02.24 - Crews are excavating and clearing the site,

4.17.24

 

 

  442 Hits
442 Hits

Texas Handcrafted Shutters

Texas Handcrafted Shutters | 6,000 SF Office/Warehouse Buildout | Katy, TX

11.01.24 - Crews are taping and floating the interior walls. Millwork is underway,

C1F31BDB 6E24 43C3 8B4A 5FF98B353A4A copy

11.01.24 2

11.01.24

 

10.17.24 - Crews are building out a 6,000 SF office/warehouse for Texas Handcrafted Shutters. This buildout is within our Katy Commercial Suites.

TXHandcraftedShutters

TXHandcraftedShutters 2

TXHandcraftedShutters 3

TXHandcraftedShutters 4

TXHandcraftedShutters 5

TXHandcraftedShutters 6

TXHandcraftedShutters 7

 

 

  291 Hits
291 Hits

Scholl Lumber

Scholl Lumber | 32,000 SF Office/Warehouse and 42,000 SF Lumber Canopy | Houston, TX

10.11.24 - Crews have progressed to sheeting the building,

10.11.24

10.11.24 2

10.11.24 3

 

10.03.24 - Erectors are hanging steel as pond work continues,

1A6DD6C2 67A8 4556 8FBE B10836198264 copy

CA200FAE 932E 4648 A456 9B5DCBE63965 copy

37ACEE67 0D5B 4AB9 B02F D69C1A4FC9DE copy

9.23.24 - The foundation has cured,

9.23

9.14.23 - Crews are pouring the building foundation,

9.14

9.10.23 - Crews are forming for the foundation pour,

F2C5C988 8AE1 4AB1 A2CD 1C35586C6032 copy

8.14.24 - Storm and sewer work continue. Crews are working on the pond and forming the pad,

8.14.24

8.05.24 - Sitework continues. Prepping for the future pad.

8.05.24

6.28.24 - The walls have cured,

E5B9F442 0D6A 4392 89FC F0D7733DA1DE copy

6.20.24 - Crews continue to work on the fencing and the pond,

1A8FC363 CE9E 4445 BE0D 3D746ECB1163 copy

6.10.24 -

58A97347 B702 41AF 8827 21D24EA14843 copy

6.08.24 - Working on the fence,

DE7A23F0 5933 440E 8C68 4554FE47CC00 copy

 

6.06.24 - Building forms,

B9DC4118 76C7 4AA8 B55E 5B6C56577B37 copy

 

This project consists of a 32,000 SF office/warehouse combination with a 2nd floor mezzanine and office area. Phase II construction will consist of a 42,000 SF lumber canopy.

  377 Hits
377 Hits

YHS Automotive

YHS Automotive| 2,560 SF PEMB | Houston, TX

YHS Automotive is a new project located in Katy, TX. The 2,560 SF building will serve as additional service bays for YHS to perform services for its customers. The building is a single slope pre-engineered metal building with two large overhead doors, fully insulated/airconditioned and brick wainscot. The scope includes the demolition of existing paving, reworking the drainage, and pouring new site paving.

 

9.21.24 - The foundation is fully poured and curing,

9.21.24

9.21.24 2

9.20.24 - Crews are prepping for the foundation pour,

9.20.24

9.18.24 - Crewmen are pouring the piers,

9.18.24

9.11.24 - 

9.11.14

8.26.24 - The demo is underway,

21BD2F0C EEB4 405A BFAB EA6FC99FE0FA copy

6287F90E 937B 45D5 9B85 0387B41FE9B8 copy

 

  238 Hits
238 Hits

Mid-South Control Line

Mid-South Control Line | 7,150 SF Warehouse | Houston, TX

This project includes a 7,150 SF single slope warehouse, with three overhead bay doors, liner panel, a fully insulated roof and fully insulated walls.

 

9.16.24 - The foundation was poured this morning and is curing,

IMG 2024 09 16 08 09 57 914 copy

IMG 2024 09 16 03 32 35 389 copy

 

9.13.24 -  Crews are forming the pad for the foundation pour,

IMG 2024 09 13 14 26 36 681 copy

 

9.10.24 - Crewmen are pouring piers,

IMG 2024 09 10 14 11 49 855 copy

 

8.26.24 - Crewmen are pouring the truck well walls,

IMG 2024 08 26 11 33 59 620 copy

 

8.14.24 - Crewmen are pouring the loading dock,

IMG 2024 08 14 06 37 14 389 copy

 

 

  207 Hits
207 Hits

O'Neills Inflight Catering

O'Neills Inflight Catering | 10,000 SF Interior Demo and Remodeling | Houston, TX

8.23.24 - Fire inspections are underway. The epoxy flooring is complete,

oneillsaug23

oneillsaug23 2

oneillsaug23 3

oneillsaug23 4

 

8.19.24 - Kitchen equipment installation and electrical trim out work continues,

oneillsaug16

oneillsaug19 2

oneillsaug19 3

oneillsaug19 4

oneillsaug19 5

oneillsaug19

 

8.13.24 - Kitchen work continues. The warehouse is clean and epoxy flooring will follow.

oneillsaug13

oneillsaug13 2

oneillsaug13 7

oneillsaug13 3

oneillsaug13 4

oneillsaug13 5

oneillsaug13 6

oneillsaug13 8

oneillsaug13 9

oneillsaug13 10

 

8.09.24 - Sign installation is underway. The kitchen is nearing completion,

oneillsaug9

oneillsaug9 2

oneillsaug9 3

 

8.07.24 - Kitchen equipment installation continues,

oneillsaug7

 

8.06.24 - Electrical work continues, flooring is nearing completion, the exterior canopy is installed,

oneillsaug6 2

oneillsaug6 3

oneillsaug6 4

oneillsaug6

7.30.24 - Parking curbs are installed, flooring continues, and restroom partition installation is nearing completion,

oneillsjuly30 2

oneillsjuly30 3

oneillsjuly30 4

oneillsjuly30 5

oneillsjuly30

7.26.24 - Flooring continues,

oneillsjuly26

oneillsjuly26 2

 

7.22.24 -

oneillsjuly22 2

oneillsjuly22 3

oneillsjuly22 4

oneillsjuly22 5

oneillsjuly22

7.17.24 - Painting continues,

oneillsjuly17 2

oneillsjuly17 3

oneillsjuly17

7.16.24 -

oneillsjuly16 2

oneillsjuly16 3

oneillsjuly16

7.12.24 - Lights are on,

9D170B89 6B40 4D36 8CAA 1BB621630B0D copy

oneillsjuly12 2

oneillsjuly12

7.10.24 -

oneillsjuly10

oneillsjuly10 2

F01DE201 5380 4C29 8768 EA31EE70012C copy

7.02.24- Inspections are complete and requirements are met, so ceiling tile installation and final clean will follow,

oneills july

oneills july2

 

6.28.24 - Kitchen equipment arrived, restroom partitions are in place, and the final painting is complete,

oneills june28

oneills june28 4

oneills june28 3

oneills june28 2

oneills june28 5

 

6.17.24 - Tile installation is underway,

oneills jun17

6.10.24 - Exterior trim is complete. Ceiling grid installation is complete. Electricians trim out the interior,

oneills june

oneills june2

5.08.24 - Crews are taping, floating, and sanding interior walls,

oneills may

oneills may2

oneills may3

 

4.26.24 - Plumbers are roughing in the plumbing as additional crews begin sheetrocking the interior walls,

oneills april

oneills april2

oneills april3

 

 

3.01.24 - Warehouse steel painting is complete. Crews are currently installing the insulated metal wall panels, 

oneills mar

2.01.24 - Interior buildout demolition continues,

63DE5FC1 A9EB 462C 9C7C 3FA1F1CBB465

oneills feb

B59413EF BE72 46BC 9007 FC783A8CCA02

 

12.04.23 - MEP interior demolition is underway, 

EC92A7F6 F9AA 4037 B919 BF33B94EC160

6C40F787 DA61 4BF4 8DB9 7FEF9B93C469

 This project includes the renovating of an existing 10,000 SF warehouse for commercial kithcen use.

 

 

  1321 Hits
1321 Hits

Independence Business Park Phase 3

Independence Business Park Phase 3

6.24.24 - Final interior photos,

june 24 2024

june 24 2024 2

june 24 2024 4

june 24 2024 8

june 24 2024 11

june 25 2024 5

 

6.11.24 - 

June 11 2024 copy

5.29.24 - Landscaping is installed for both buildings,

May 29 copy

5.17.24 -  Lights are on,

May 17 2024 copy

3.05.24 - Landscaping is soon to follow,

March 2024

2.24.24 - Sidewalks are poured,

Feb 26 2024 copy

 

2.22.24 - Paving is poured and cured. Curbs have been poured. Masonry work is complete.

Feb 22 2024 copy

 

2.06.24 - Sitework is underway preparing for the next paving pour. Interior buildout continues,

Feb 2024

 

1.11.24 - Masonry work continues. The metal sheeting and trim is complete and windows are installed. Interior buildout continues,

Jan

12.11.23 - The building is fully sheeted and the interior buildout is underway. The parking has been poured and is curing,

Dec

11.02.23 - All iron is in place and sheeting is underway,

Nov 2 copy

10.02.23 - M&M Erectors are haning the main frame collumns,

Oct

9.01.23 - Sitework continues,

sept copy

 

7.17.23 -  Site crews began to scrape the site for the third phase of the Independence Business Park for Finial Group. We are building three office / warehouse buildings total (Building 2, Building 6, and Building 7, each being pre-engineered metal buildings with horizontal architectural panels and limestone offices. Bldg 2 will be 46,378 SF with a 2,855 SF office. Building 6 will be a 18,525 SF crane-ready building with a 2,025 SF office, and Building 7 will be a 25,425 SF crane-ready building with a 2,025 SF office.

image3

  2055 Hits
2055 Hits

Katy Industrial Suites

Katy Industrial Suites | 23,660 SF New Custom Office Condos | Katy, TX

The Katy Commercial Suites are finished and are available for Lease or Sale. Spaces range from 2,088 SF to 12,529 SF,

IMG 0853 copy

IMG 0856 copy

IMG 0857 copy

IMG 0858 copy

IMG 0859 copy

IMG 0860 copy

IMG 0864 copy

IMG 0866 copy

IMG 0872 copy

IMG 0873 copy

IMG 0874 copy

IMG 0884 copy

1000093261

1000093260

 

10.04.23 - The landscaping is scheduled for this week, and the power is to be turned on this week.

IMG 6913 copy

IMG 6916 copy

IMG 6917

IMG 6918 copy

IMG 6919 copy

IMG 6921 copy

IMG 6923 copy

 

4.20.23 - The last of the paving was poured last night. Erectors continue to sheet the buildings,

IMG 2023 04 20 01 40 57 974 copy

IMG 2023 04 20 02 29 28 189 copy

 

3.22.23 - Erectors began hanging steel this week. Half of the paving was poured this morning,

katy industrial suites 1 copy

katy industrial suites 2 copy

 

10.13.22 - Site crewmen broke ground this week on the Katy Industrial Condos. Crewmen have scraped the site and are beginning the pads,

1 copy

2 copy

3 copy

4 copy

 

9.22.22 - Our crews are breaking ground this week on a new Industrial Condominium project in Katy, TX. Two 11,830 SF units are under construction in the Katy-Hockley Business Park Development (4107 and 4109 Katy Hockley Rd). The condominiums will total 23,660 SF and will be ready Q2 2023.

02 copy

01 copy

03 copy

  4599 Hits
4599 Hits

Commons at Timber Creek

The Commons at Timber Creek | Two 13,020 SF Flex Space Office/Warehouses | Friendswood, TX

Construction is complete on these Industrial Suites. 

7DBE5FCE 415C 4FB7 8FEC 6813958249BF copy

C54CBE82 2B9F 4831 844B 58184C1D70D4 copy

1AC79FFA 136C 4CF4 978E 0E538F1E99B6

297CA0BA 7425 418D AFCA 30611961E5A0 copy

EFA20993 182E 4C41 9EAB 4C3B78D3F3E5 copy

7.17.23 - The stucco and stone is complete. Crewmen are installing glass.

IMG 6165 copy

IMG 6166 copy

IMG 6167 copy

IMG 6168 copy

IMG 6169 copy

IMG 6173 copy

IMG 6174 copy

 

4.14.23 -The masons started their work on the stucco. This project is on schedule to be completed in May.

1

 

3.01.22 - Erectors continue to hang steel. The framing crews began framing the front facades. The paving crew will start pouring the paving soon,

15 copy

14 copy

16 copy

 

12.02.22 - Crews began sheeting the buildings,

6

1

12

 

11.17.22 - Crews are erecting the first of the 12,000 SF flex office/warehouse spaces,

Commons4 copy

 

11.06.22 - Crewmen poured the first pad for this project. Spaces are available for sale or lease and range from 3,000 SF to 12,000 SF.

02 copy

01 copy

COMMONS 1 copy

3 copy

Friendswood4 copy

Friendswood3 copy

  3693 Hits
3693 Hits

Big Industry Boat and RV Storage

Big Industry Boat and RV Storage | 100,000 SF | Friendswood, TX

Construction of these storage units is complete,

5F00CF3D BB5C 44D3 970F F01D32C3D27C 1

95438093 0DAA 4337 B6DB 610A3B8A6BE8

B732D5FF DF64 4CFD A272 06183533978E copy

4D48B492 AB4D 4B85 98C5 A2422E57E81B copy

337F9C28 C444 4A1B 911C 9824A9B48A47 copy

1873F435 7E40 414F A0F3 E56E2D339286 copy

4848A412 5889 4A10 A47D 000F016DA29B copy

A5DA13F9 8877 4941 84F7 2CD1EC967E8E copy

D540CB38 DF58 47DA 83E0 15D0D0A9D0F5 copy

E1A1BC64 85FA 4188 B07D CB41EA70F00A copy

 

4.14.23 - Crews are hanging steel for the next storage unit,

DJI 0019 copy 

DJI 0023 copy

 

3.01.22 - The first two buildings are fully sheeted and trimmed. Sheeting continues on the third storage unit,

4 copy

5 copy

12.02.22 - This boat and RV storage park will include 100,000 SF of storage within a total of 13 buildings. The first two buildings are poured,

7

8

9

  1851 Hits
1851 Hits

Big City Manufacturing

Big City Manufacturing | 23,000 SF | Friendswood, TX

1.23.24 - Final clean is complete. Landscaping is installed.

0BD6C680 52A8 4787 8BEF A644FB29AC8E copy

797FAD6A C23E 4A68 B2E7 D90FC9C38964 copy

884C688C 603B 4BDB 89EA 9C98ED21AA07 copy

939DEC6C 288A 4EE4 954C 20C25338B881 copy

C331B695 3575 49DB 86F5 DCABC72FF462 copy

31035EC2 0FEB 4E42 A95D AF30549D04F9 copy

61D807FB CAFD 4AE1 A6BA 6770C95B70D8 copy

 

 

D3AA3738 4014 4D82 95B0 3C1DD4069A3A copy

D81F2F89 F9BA 433B A89C 29C492DC3C6A copy

F490AF31 9C19 4F45 8F5D F92E54F27F3E copy

04208C60 FE41 40AC AC2D 6ABBBB3455FE copy

BF53357C 94CF 4F2D 9D91 8F5C71965574 copy

122E8930 ADA4 48CA 902B 62E5E69ACBCD copy

81F10C2A 4D7A 4063 8C28 994E01EC4E7C copy

 

12.14.23 - Parking area striping is complete,

09AE6B39 8AB1 45C5 ADF8 561E57D210AD copy

9AF3ACD3 CF26 4ACC 9DC4 941AE688EF56 copy

36E4F666 9456 4E39 8271 415C602837BB

3066A27C 1B03 4852 B0A9 919768EA95F1 copy

525669C0 C0A1 4694 9C1A FF83070A442D copy

 

11.29.23 - Glass installation is complete and the ceilings are installed. Power should be turned on next with an expected completion set for next month,

IMG 7242 copy

IMG 7234 copy

IMG 7236 copy

IMG 7237 copy

IMG 7238 copy

IMG 7239 copy

IMG 7240 copy

 

10.25.23 - Interior crews are hanging sheetrock. Concrete crewmen are getting ready to pour the equipment pad,

IMG 7097 copy

IMG 7096 copy

IMG 7095 copy

IMG 7094 copy

IMG 7093 copy

IMG 7092 copy

IMG 7091 copy

IMG 7090 copy

 

7.25.23 - Crews poured the foundation this morning.

IMG 6281 copy

IMG 6272 copy

 

7.20.23 - Crewmen are preparing for next week's pour,

image11 copy

IMG 6222 copy

IMG 6218 copy

 

5.25.23 - Crews are breaking ground on Big City Manufacturing's new facility in Industry Park. This Design/Build project includes a fully air conditioned shop and 3,000 SF of finished office space,

20223 Binford Flipped.jpg copy

IMG 5673.jpg copy

IMG 5676.jpg copy

  3050 Hits
3050 Hits

SiteOne Friendswood Expansion

SiteOne Friendswood Expansion | 12,000 SF | Friendswood, TX

1.23.24 - This project is complete,

81E6EF1E 68B6 49E4 AF8D CF63E30F6433 copy

44C23466 4822 4B40 9B5C 24DE05500C1A

SiteOneFriendswood

6C25955D B083 42AE 9C26 2CA7250A7554 copy

 

12.14.23 - M&M Erectors continue to sheet the building,

2AF6A487 99CC 4D15 95B0 1FA381041CBB copy

4EC6DBF7 6771 4738 A6F6 E117E473EFD1 copy

739F5833 B49B 4B07 A2A1 06681B853954 copy

57759ABC A2F6 41B0 A5E5 E2CDD08948F2 copy

31701325 9D7B 44D2 B02E 113E373C05A7

 

11.29.23 - The paving was poured this morning and erectors are hanging steel,

IMG 7243 copy

IMG 7245 copy

 

11.03.23 - The slab is poured for the new 12,000 SF expansion of their Friendswood location. The concrete crew is laying out the paving and the erectors will begin hanging steel next week.

IMG 7170 copy

IMG 7169 copy

IMG 7167 copy

IMG 7166 copy

IMG 7165 copy

 

  1174 Hits
1174 Hits

Traders Village Houston

Traders Village Houston | PEMB | Houston, TX

1.18.24 - This project is complete,

1.18.24 TradersVillage 4

1.18.24 TradersVillage

1.18.24 TradersVillage 2

1.18.24 TradersVillage 3

1.18.24 TradersVillage 5

1.18.24 TradersVillage 6

 

12.19.23 - The steel is erected and crews are making fast progress sheeting the building,

12.19.23 TradersVillage 4

12.19.23 TradersVillage 3

12.19.23 TradersVillage 2

12.19.23 TradersVillage

 

 

  623 Hits
623 Hits

Mid-South Control Line

Mid-South Control Line | Building Addition | Houston, TX

10.26.23 - 

mid south 10.26

mid south 10.26 2

 

10.25.23 - 

mid south 10.25

mid south 10.25 2

mid south 10.25 3

 

9.25.23 - Crews are installing liner panels and are trimming the building,

mid south 9.25

mid south 9.25 2

mid south 9.25 3

 

9.13.23 - Crews are hanging the pre-assembled roof sections,

mid south 9.13

 

9.07.23 - The pad is cured and sawcut,

mid south 9.07

 

9.02.23 - Crews are pouring the foundation,

20230902 030057 copy

 

8.29.23 - Drilling and pouring piers,

mid south 8.29

mid south 8.14 3

 

8.14.23 - Setting storm drains,

mid south 8.14

mid south 8.14 2

 

 

  484 Hits
484 Hits

Humble Sign Co.

Humble Sign Co. | 35,722 SF | Humble, TX

5.25.23 - Interior crews continue to hang sheetrock. The paving crew is laying out the remainder of paving to be poured,

1 copy

2 copy

3 copy

4 copy

5 copy

6 copy

6 copy

7 copy

8 copy

9 copy

10 copy

11 copy

12 copy

13 copy

 

3.08.23 - Erectors completed their work hanging the steel. The fire sprinkler contract are hanging pipe. The dirt crewmen are cutting grades,

9 copy

8 copy

7 copy

6 copy

5 copy

4 copy

3 copy

2 copy

1 copy

 

2.08.23 - M&M Erectors are hanging steel for the new facility,

humblesign2.08

humblesign2.08 2

 

1.17.23 - Crews are pouring the foundation for Humble Sign’s new 35,722 SF facility. Their new facility includes a two-story office and a crane-served warehouse for manufacturing. We built for Humble Sign in 2018 and are excited to be working with them again.  

10

4

2

  1508 Hits
1508 Hits

Webb's Automotive

Webb's Automotive | 2,500 SF Free-standing Oil Service Center | Cypress, TX

3.09.23 - We enjoyed being a part of Webb's Automotive ribbon cutting yesterday featuring their new expansion,

WebbsAuto ribbon cutting

 

1.27.23 - Erectors trimmed the new expansion,

IMG 2023 01 27 15 25 29 042 copy

IMG 2023 01 27 15 25 33 792 copy

IMG 2023 01 27 15 25 49 821 copy

IMG 2023 01 27 15 26 10 030 copy

IMG 2023 01 27 15 27 05 941 copy

IMG 2023 01 27 15 27 17 509 copy

 

11.18.22 - Crewmen poured the foundation for Webb's Automotive's new oil service center. We built Webb's Automotive's origional auto repair and oil change service facility 11 years ago. It is such a blessing to be doing additional work for past customers,

webbs auto pour

webbs auto pour 3

webbs auto pour 4

webbs auto pour 5

  1826 Hits
1826 Hits

Premier Cryogenics

Premier Cryogenics | New 26,000 SF 20-ton Crane-served Manufacturing Facility | LaPorte, TX

10.13.22 - Erectors are getting close to closing in the South end of the building,

1

2

4

7

 

9.29.22 - Exterior sheeting and interior insulated sheeting are underway,

7

6

5

9.27.22 - Additional paving is poured. M&M Erectors have erected the steel and are installing the wall sheeting,

1

10

12

9.22.22 - Erectors are assembling and lifting the roof sections,

1

9.19.22 - Erectors are shaking out the steel,

1

2

 

  1855 Hits
1855 Hits

Elite RV

Elite RV | 70,000 SF Concierge Service Storage Center | Waller, TX

7.06.22 - This project is complete,

EliteRV

EliteRV2

EliteRV3

EliteRV4

EliteRV5

EliteRV6

EliteRV 7.06

EliteRV 7.06 2

EliteRV 7.06 3

EliteRV 7.06 4

EliteRV 7.06 5

6.02.22 - Masonry work is underway, in addition to electrical and the office build-out,

IMG 6889

IMG 6880

IMG 6885

IMG 6890

IMG 6894

IMG 6895

IMG 6899

IMG 6902

 

5.11.22 - Canopies are being installed. M&M is trimming out the wash bay building. The asphalt drive is complete,

EliteRV copy

EliteRV2 copy

EliteRV3 copy

EliteRV4 copy

EliteRV5 copy

EliteRV6 copy

EliteRV7 copy

EliteRV8 copy

EliteRV9 copy

EliteRV10 copy

EliteRV11 copy

EliteRV12 copy

EliteRV13 copy

 

3.18.22 - Erectors continue to sheet the building. The concrete crew is scheduled to pour the parking lot next week,

Elite RV 3.18 4

Elite RV 3.18 2

Elite RV 3.18 5

Elite RV 3.18

 

3.02.22 - Erectors continue to hang steel. The pre-assembles are complete and crews are filling in the intermediate bays,

1

7

9

2.15.22 - Erectors are hanging sections of roof,

IMG 3006

IMG 3016

IMG 3019

 

1.19.22 - Crews are pouring the second half of the foundation,

Elite RV 2nd half slab

Elite RV 2nd half slab 4

 

11.11.21 - Site work is underway for Elite RV's new 70,000 SF conceirege service storage center for motorcoaches,

Elite RV rendering

Elite RV rendering aerial

5

6

10

  3095 Hits
3095 Hits

Closner Equipment Co.

Closner Equipment Co. | New Office, Warehouse, Repair Bays and Wash Bays | Waller, TX

7.06.22 - The pad and utilities are complete. Crews will begin drilling the piers this week,

Closner 7.06

Closner 7.06 2

Closner 7.06 3

Closner 7.06 4

 

5.16.22 - Sitework continues,

IMG 2022 05 16 15 09 46 728

IMG 2022 05 16 15 07 11 795

IMG 2022 05 16 15 07 24 563

IMG 2022 05 16 15 08 23 044

 

5.15.22 - The project consists of erecting 4 buildings for the Closner Equipment Co.

The buildings are Office, Warehouse, Repair Bays, and a Wash Bay.

Total is about 6.5 acres with new grading, drainage, and paving plan. Lot will be fenced with automatic gates installed.

Detention pond had 858 cubic yards of dirt removed per the civil engineering plans for the offset of drained water. This portion of the project is complete.

 

  2175 Hits
2175 Hits