twitter facebook linkedin

More than 35 years
of experience in Texas

previous arrow
next arrow
Slider

O'Neills Inflight Catering

O'Neills Inflight Catering | 10,000 SF Interior Demo and Remodeling | Houston, TX

8.23.24 - Fire inspections are underway. The epoxy flooring is complete,

oneillsaug23

oneillsaug23 2

oneillsaug23 3

oneillsaug23 4

 

8.19.24 - Kitchen equipment installation and electrical trim out work continues,

oneillsaug16

oneillsaug19 2

oneillsaug19 3

oneillsaug19 4

oneillsaug19 5

oneillsaug19

 

8.13.24 - Kitchen work continues. The warehouse is clean and epoxy flooring will follow.

oneillsaug13

oneillsaug13 2

oneillsaug13 7

oneillsaug13 3

oneillsaug13 4

oneillsaug13 5

oneillsaug13 6

oneillsaug13 8

oneillsaug13 9

oneillsaug13 10

 

8.09.24 - Sign installation is underway. The kitchen is nearing completion,

oneillsaug9

oneillsaug9 2

oneillsaug9 3

 

8.07.24 - Kitchen equipment installation continues,

oneillsaug7

 

8.06.24 - Electrical work continues, flooring is nearing completion, the exterior canopy is installed,

oneillsaug6 2

oneillsaug6 3

oneillsaug6 4

oneillsaug6

7.30.24 - Parking curbs are installed, flooring continues, and restroom partition installation is nearing completion,

oneillsjuly30 2

oneillsjuly30 3

oneillsjuly30 4

oneillsjuly30 5

oneillsjuly30

7.26.24 - Flooring continues,

oneillsjuly26

oneillsjuly26 2

 

7.22.24 -

oneillsjuly22 2

oneillsjuly22 3

oneillsjuly22 4

oneillsjuly22 5

oneillsjuly22

7.17.24 - Painting continues,

oneillsjuly17 2

oneillsjuly17 3

oneillsjuly17

7.16.24 -

oneillsjuly16 2

oneillsjuly16 3

oneillsjuly16

7.12.24 - Lights are on,

9D170B89 6B40 4D36 8CAA 1BB621630B0D copy

oneillsjuly12 2

oneillsjuly12

7.10.24 -

oneillsjuly10

oneillsjuly10 2

F01DE201 5380 4C29 8768 EA31EE70012C copy

7.02.24- Inspections are complete and requirements are met, so ceiling tile installation and final clean will follow,

oneills july

oneills july2

 

6.28.24 - Kitchen equipment arrived, restroom partitions are in place, and the final painting is complete,

oneills june28

oneills june28 4

oneills june28 3

oneills june28 2

oneills june28 5

 

6.17.24 - Tile installation is underway,

oneills jun17

6.10.24 - Exterior trim is complete. Ceiling grid installation is complete. Electricians trim out the interior,

oneills june

oneills june2

5.08.24 - Crews are taping, floating, and sanding interior walls,

oneills may

oneills may2

oneills may3

 

4.26.24 - Plumbers are roughing in the plumbing as additional crews begin sheetrocking the interior walls,

oneills april

oneills april2

oneills april3

 

 

3.01.24 - Warehouse steel painting is complete. Crews are currently installing the insulated metal wall panels, 

oneills mar

2.01.24 - Interior buildout demolition continues,

63DE5FC1 A9EB 462C 9C7C 3FA1F1CBB465

oneills feb

B59413EF BE72 46BC 9007 FC783A8CCA02

 

12.04.23 - MEP interior demolition is underway, 

EC92A7F6 F9AA 4037 B919 BF33B94EC160

6C40F787 DA61 4BF4 8DB9 7FEF9B93C469

 This project includes the renovating of an existing 10,000 SF warehouse for commercial kithcen use.

 

 

Mid-South Control Line
Independence Business Park Phase 3

Related Posts

By accepting you will be accessing a service provided by a third-party external to https://northwindsconst.com/