10.26.23 -
10.25.23 -
9.25.23 - Crews are installing liner panels and are trimming the building,
9.13.23 - Crews are hanging the pre-assembled roof sections,
9.07.23 - The pad is cured and sawcut,
9.02.23 - Crews are pouring the foundation,
8.29.23 - Drilling and pouring piers,
8.14.23 - Setting storm drains,