twitter facebook linkedin

More than 35 years
of experience in Texas

previous arrow
next arrow
Slider

Northwinds Construction

View important updates by Northwinds Construction

Katy Industrial Suites

Katy Industrial Suites | 23,660 SF New Custom Office Condos | Katy, TX

The Katy Commercial Suites are finished and are available for Lease or Sale. Spaces range from 2,088 SF to 12,529 SF,

IMG 0853 copy

IMG 0856 copy

IMG 0857 copy

IMG 0858 copy

IMG 0859 copy

IMG 0860 copy

IMG 0864 copy

IMG 0866 copy

IMG 0872 copy

IMG 0873 copy

IMG 0874 copy

IMG 0884 copy

1000093261

1000093260

 

10.04.23 - The landscaping is scheduled for this week, and the power is to be turned on this week.

IMG 6913 copy

IMG 6916 copy

IMG 6917

IMG 6918 copy

IMG 6919 copy

IMG 6921 copy

IMG 6923 copy

 

4.20.23 - The last of the paving was poured last night. Erectors continue to sheet the buildings,

IMG 2023 04 20 01 40 57 974 copy

IMG 2023 04 20 02 29 28 189 copy

 

3.22.23 - Erectors began hanging steel this week. Half of the paving was poured this morning,

katy industrial suites 1 copy

katy industrial suites 2 copy

 

10.13.22 - Site crewmen broke ground this week on the Katy Industrial Condos. Crewmen have scraped the site and are beginning the pads,

1 copy

2 copy

3 copy

4 copy

 

9.22.22 - Our crews are breaking ground this week on a new Industrial Condominium project in Katy, TX. Two 11,830 SF units are under construction in the Katy-Hockley Business Park Development (4107 and 4109 Katy Hockley Rd). The condominiums will total 23,660 SF and will be ready Q2 2023.

02 copy

01 copy

03 copy

  4487 Hits
4487 Hits

Commons at Timber Creek

The Commons at Timber Creek | Two 13,020 SF Flex Space Office/Warehouses | Friendswood, TX

Construction is complete on these Industrial Suites. 

7DBE5FCE 415C 4FB7 8FEC 6813958249BF copy

C54CBE82 2B9F 4831 844B 58184C1D70D4 copy

1AC79FFA 136C 4CF4 978E 0E538F1E99B6

297CA0BA 7425 418D AFCA 30611961E5A0 copy

EFA20993 182E 4C41 9EAB 4C3B78D3F3E5 copy

7.17.23 - The stucco and stone is complete. Crewmen are installing glass.

IMG 6165 copy

IMG 6166 copy

IMG 6167 copy

IMG 6168 copy

IMG 6169 copy

IMG 6173 copy

IMG 6174 copy

 

4.14.23 -The masons started their work on the stucco. This project is on schedule to be completed in May.

1

 

3.01.22 - Erectors continue to hang steel. The framing crews began framing the front facades. The paving crew will start pouring the paving soon,

15 copy

14 copy

16 copy

 

12.02.22 - Crews began sheeting the buildings,

6

1

12

 

11.17.22 - Crews are erecting the first of the 12,000 SF flex office/warehouse spaces,

Commons4 copy

 

11.06.22 - Crewmen poured the first pad for this project. Spaces are available for sale or lease and range from 3,000 SF to 12,000 SF.

02 copy

01 copy

COMMONS 1 copy

3 copy

Friendswood4 copy

Friendswood3 copy

  3616 Hits
3616 Hits

Closner Equipment Co.

Closner Equipment Co. | New Office, Warehouse, Repair Bays and Wash Bays | Waller, TX

7.06.22 - The pad and utilities are complete. Crews will begin drilling the piers this week,

Closner 7.06

Closner 7.06 2

Closner 7.06 3

Closner 7.06 4

 

5.16.22 - Sitework continues,

IMG 2022 05 16 15 09 46 728

IMG 2022 05 16 15 07 11 795

IMG 2022 05 16 15 07 24 563

IMG 2022 05 16 15 08 23 044

 

5.15.22 - The project consists of erecting 4 buildings for the Closner Equipment Co.

The buildings are Office, Warehouse, Repair Bays, and a Wash Bay.

Total is about 6.5 acres with new grading, drainage, and paving plan. Lot will be fenced with automatic gates installed.

Detention pond had 858 cubic yards of dirt removed per the civil engineering plans for the offset of drained water. This portion of the project is complete.

 

  2086 Hits
2086 Hits

Independence Business Park

Independence Business Park (Finial Group)| 43,000 SF of New Office/Warehouses | Houston, TX

This project includes two ground-up spec office/warehouses totaling 43,000 SF. Scope of project also includes extending the business park's private drive and utilities.  

3.02.22 - Buildings 4 and 8 are completed,

6812 8 Bldg 8 2

6811 4 3

6812 8 Bldg 8 4

6812 8 Bldg 8 5

 

2.18.22 - Wrapping up work on Buildings 4 and 8,

9

5

2

4

6

11

 

12.29.21 - Stucco and masonry to begin. Landscaping continues for Bldg 4 and began today for Bldg 8. Electricians are digging up the underground conduit to AT&T's conduit at both bldgs,

12.29.21 2

12.29.21 3

12.29.21 4

12.29.21

 

12.23.21 - Ceiling tile installation continues for Buildings 4 & 8, fixtures are installed in both buildings, receptacles and can lights are going in today in both buildings, and crews are hooking up the condenser units for Buildings 4 and 8,

12.22.21 2

12.22.21

 

12.16.21 - Flooring continues,

12.16.21 3

12.16.21 2

12.16.21 4

12.16.21 5

12.16.21

11.05.21 - Waiting on one piece of glass to be installed above the door on Building 8. Plumbers are ready for fixtures as soon as the floors are installed. Electrial work continues for both buildings. 

DJI 0726

DJI 0725

DJI 0717

DJI 0706

 

 

 

10.29.21 - The OH door installation continues for Building 8. Plumbers are also installing the water heater and pipe for Building 8. Electricians continue their work on Buildings 4 and 8,

10.29.21

10.29.21 4

10.29.21 6

10.22.21 - Crews cleaned and backfilled around the seven new concrete drainage flumes. Crews are installing lights and ceiling grid in Buildng 4. Waiitng on AC materials for buildings 4 and 8,

Bldg4 1

Bldg4 2

Bldg4 3

Bldg8

Bldg8 3

Bldg8 5

 

9.07.21 - Northwinds crewmen are working to back fill the south side of Bldg 8, next to the drainage ditch, and dress it up. M&M Erectors continue the wall panel installation on Bldg 4,

Screenshot 2021 09 07 094643

Screenshot 2021 09 07 094549

Screenshot 2021 09 07 094706

Screenshot 2021 09 07 094720

Screenshot 2021 09 07 094738

Screenshot 2021 09 07 094752

Screenshot 2021 09 07 095130

 

8.24.21 - Erectors are lifting Bldg #4's roof,

BLDG4

BLDG4 8.24 2

BLDG4 8.24

 

8.18.21 - Paving was poured for Bldg #8. Erectors are lifting Bldg #4,

Bldg 8 paving

Bldg 8 paving 4

Bldg 8 paving 6

Bldg 4

Bldg 4 3

 

7.24.21 - Foundation was poured this morning for Bldg #4,

DJI 0187

DJI 0207

7.02.21 - Crewmen continue to lay out the sub-sub grade in the paving areas around Bldg. 4 & 8, and are cutting to grade to prepare for select fill,

Screenshot 2021 07 06 094600

Screenshot 2021 07 06 094631

Screenshot 2021 07 06 094651

Screenshot 2021 07 06 094703

 

6.25.21 - We are resuming select fill in the paving areas around pad #8. Cutting the paving sub grade in the west end of pad #4 to be able to get a minimum of 8” of select fill and compacted. Plumbers are backfilling trenches.

 

6.12.21 - Windrowing the select fill on Pad 4 and on Pad 8 to help pull the moisture out. Regrading and compacting to get ready for their test on Monday morning. Working on the ditch on the north side of BLDG. 8. Shaping and grading to drain to the pond inlet.

6.12.21

 

6.11.21 - Site crewmen are laying down the select fill that was stock piled yesterday on Pad 4 and began laying down the select fill that was stock piled yesterday on Pad 4. Crews started the first lift on pad 8, compacting in lifts. The plumbers continue working on the 8” water tie in and continued digging their trench. 

6.11.21

 

6.10.21 - Site crewmen began the select fill in Pad 4 and are compacting in lifts.

6.10.21

6.10.21 1

6.09.21 - Crews are cutting bldg. pad 4 & 8 to sub grade (in preparation for select fill). Running the 324 over pad 8 to compact it. Back filling stabilized. Back filling stabilized sand over the 2 culverts. Began the layout and grading on the north side ditch,

6.09.21 1

6.09.21

 

6.08.21 - Cutting bldg. pad 4 to sub grade and starting on pad 8 to prepare for select fill. Running the Roller and 324 over pad 4 to compact it.

6.08.21

6.08.21 1

 

6.07.21 - Starting the 24” & 15” coverts - excavating to grade, building up hdpe bed with stabilized sand, laying the pipe and back fill to 6” from top of pipe for city inspections. Cutting bldg. pad #4 to sub grade to prepare for select fill. 

6.07.21

 

 

  2864 Hits
2864 Hits