twitter facebook linkedin

More than 35 years
of experience in Texas

previous arrow
next arrow
Slider

Northwinds Construction

View important updates by Northwinds Construction

Independence Business Park

Independence Business Park (Finial Group)| 43,000 SF of New Office/Warehouses | Houston, TX

This project includes two ground-up spec office/warehouses totaling 43,000 SF. Scope of project also includes extending the business park's private drive and utilities.  

3.02.22 - Buildings 4 and 8 are completed,

6812 8 Bldg 8 2

6811 4 3

6812 8 Bldg 8 4

6812 8 Bldg 8 5

 

2.18.22 - Wrapping up work on Buildings 4 and 8,

9

5

2

4

6

11

 

12.29.21 - Stucco and masonry to begin. Landscaping continues for Bldg 4 and began today for Bldg 8. Electricians are digging up the underground conduit to AT&T's conduit at both bldgs,

12.29.21 2

12.29.21 3

12.29.21 4

12.29.21

 

12.23.21 - Ceiling tile installation continues for Buildings 4 & 8, fixtures are installed in both buildings, receptacles and can lights are going in today in both buildings, and crews are hooking up the condenser units for Buildings 4 and 8,

12.22.21 2

12.22.21

 

12.16.21 - Flooring continues,

12.16.21 3

12.16.21 2

12.16.21 4

12.16.21 5

12.16.21

11.05.21 - Waiting on one piece of glass to be installed above the door on Building 8. Plumbers are ready for fixtures as soon as the floors are installed. Electrial work continues for both buildings. 

DJI 0726

DJI 0725

DJI 0717

DJI 0706

 

 

 

10.29.21 - The OH door installation continues for Building 8. Plumbers are also installing the water heater and pipe for Building 8. Electricians continue their work on Buildings 4 and 8,

10.29.21

10.29.21 4

10.29.21 6

10.22.21 - Crews cleaned and backfilled around the seven new concrete drainage flumes. Crews are installing lights and ceiling grid in Buildng 4. Waiitng on AC materials for buildings 4 and 8,

Bldg4 1

Bldg4 2

Bldg4 3

Bldg8

Bldg8 3

Bldg8 5

 

9.07.21 - Northwinds crewmen are working to back fill the south side of Bldg 8, next to the drainage ditch, and dress it up. M&M Erectors continue the wall panel installation on Bldg 4,

Screenshot 2021 09 07 094643

Screenshot 2021 09 07 094549

Screenshot 2021 09 07 094706

Screenshot 2021 09 07 094720

Screenshot 2021 09 07 094738

Screenshot 2021 09 07 094752

Screenshot 2021 09 07 095130

 

8.24.21 - Erectors are lifting Bldg #4's roof,

BLDG4

BLDG4 8.24 2

BLDG4 8.24

 

8.18.21 - Paving was poured for Bldg #8. Erectors are lifting Bldg #4,

Bldg 8 paving

Bldg 8 paving 4

Bldg 8 paving 6

Bldg 4

Bldg 4 3

 

7.24.21 - Foundation was poured this morning for Bldg #4,

DJI 0187

DJI 0207

7.02.21 - Crewmen continue to lay out the sub-sub grade in the paving areas around Bldg. 4 & 8, and are cutting to grade to prepare for select fill,

Screenshot 2021 07 06 094600

Screenshot 2021 07 06 094631

Screenshot 2021 07 06 094651

Screenshot 2021 07 06 094703

 

6.25.21 - We are resuming select fill in the paving areas around pad #8. Cutting the paving sub grade in the west end of pad #4 to be able to get a minimum of 8” of select fill and compacted. Plumbers are backfilling trenches.

 

6.12.21 - Windrowing the select fill on Pad 4 and on Pad 8 to help pull the moisture out. Regrading and compacting to get ready for their test on Monday morning. Working on the ditch on the north side of BLDG. 8. Shaping and grading to drain to the pond inlet.

6.12.21

 

6.11.21 - Site crewmen are laying down the select fill that was stock piled yesterday on Pad 4 and began laying down the select fill that was stock piled yesterday on Pad 4. Crews started the first lift on pad 8, compacting in lifts. The plumbers continue working on the 8” water tie in and continued digging their trench. 

6.11.21

 

6.10.21 - Site crewmen began the select fill in Pad 4 and are compacting in lifts.

6.10.21

6.10.21 1

6.09.21 - Crews are cutting bldg. pad 4 & 8 to sub grade (in preparation for select fill). Running the 324 over pad 8 to compact it. Back filling stabilized. Back filling stabilized sand over the 2 culverts. Began the layout and grading on the north side ditch,

6.09.21 1

6.09.21

 

6.08.21 - Cutting bldg. pad 4 to sub grade and starting on pad 8 to prepare for select fill. Running the Roller and 324 over pad 4 to compact it.

6.08.21

6.08.21 1

 

6.07.21 - Starting the 24” & 15” coverts - excavating to grade, building up hdpe bed with stabilized sand, laying the pipe and back fill to 6” from top of pipe for city inspections. Cutting bldg. pad #4 to sub grade to prepare for select fill. 

6.07.21

 

 

  2865 Hits
2865 Hits

Magellan Midstream Partners

Magellan Midstream Partners | 9,500 SF Freestanding Office and Control Center | Houston, TX

12.29.20 - This project was completed on Dec 2nd, with the exception of a few small items that are being wrapped up,

IMG 0517

IMG 0479

IMG 0518

IMG 0531

IMG 0549

IMG 0550

IMG 0552

IMG 0574

IMG 0575

IMG 0618

IMG 104

 

9.15.20 - Painters started applying the first coat of paint, and Site crewmen are making the final grade,

119513896 3870286709652798 8192365143876956359 o

119518843 3870286699652799 5056428671373765105 o

119522452 3870286689652800 4764239601070146737 o

119558215 3870286719652797 277720845147280050 o

119565518 3870286702986132 2840597188222595001 o

119587578 3870286726319463 1900187956359894981 o

119622378 3870286712986131 8064936732280126111 o

119643464 3870286742986128 364847143793880976 o

 

 

8.24.20 - Northwinds crewmen are laying base for an asphalt parking lot. Over the next two weeks, they will final grade around the building and prepare for the landscaping installation. The interior buildout continues.

IMG 4902

IMG 4901

IMG 4905

IMG 4911

IMG 4913

IMG 4915

IMG 4916

IMG 4917

IMG 4919

 

7.07.20 - Erectors continue to hang steel,

IMG 2338

IMG 2340

 

6.19.20 - The building was delivered.

 

6.17.20 - Crews are pouring the building pad,

20200617 135312850 iOS

6.10.20 - Site crewmen have completed the pad. Concrete crews began digging beams. Electricians are running service conduit,

IMG 0201

IMG 0202

IMG 0204

IMG 0205

IMG 0207

IMG 1621

 

12.27.19 - This project calls for a 9,500 SF Freestanding office and control center. The project is located in Midstream's existing terminal, on the East side of Houston. We are currently in the planning and permitting stage of this project.

  5243 Hits
5243 Hits

Duncan Aviation SR-8 Build Out

Duncan Aviation SR-8 Build Out

8.21.20 - This project is near completion,

20200730 072022 photo

20200730 072031 photo

20200803 063024 photo

20200803 063241 photo

20200803 063539 photo

20200805 090325 photo

IMG 3015

IMG 3016

IMG 7126

IMG 7130

 

7.27.20 - Crewmen are painting the plywood walls in 115 & 119, installing hardware on doors and starting the ceiling tile installation. Flooring crews have completed the VCT and cove base throughout Duncan's office areas. Electrical is complete and ready for inspection. Once the canopy is trimmed out, the remaining lighting will be completed,

7.25 2

7.25 3

7.25 4

7.25 5

7.25

7.27 2

7.27 3

7.27 4

7.27 5

7.27 7

7.27 8

7.27 9

7.27 10

7.27 11

7.27

 

 

7.20.20 - Interior painting continues. Electricians continue above-ceiling rough in and wiring of the electrical panels.

1

2

3

4

5

6

7

9

8

9

10

 

7.02.20 - Crewmen continue to run the ceiling grid and duct work. Electrical rough in has begun.

 

6.30.20 - Crews are running wall angle and hanging ceiling wires. They started running the ceiling grid. Crewmen are adding fire-rated plywood at the TV locations. AC contractor continues running hangers and assembling the AC ducts.

6.26 duncan 2

6.26 duncan 3

6.26 duncan 5

6.26 duncan 6

6.26 duncan 7

6.26 duncan 8

6.26 duncan 9

6.26 duncan 10

6.26 duncan 11

6.28.20 - This project calls for a 4,231 SF interior build out of an existing shell building (SR-8), that we constructed in 2019. Metal stud framing is underway. The Fire subcontractor began bringing the pipe drops to 1'-0" above the ceiling height.

1

2

3

4

  3603 Hits
3603 Hits

Wilson Air

Wilson Air | 28,000 SF Additional Airplane Hangar and Office | Houston, TX

10.15.19 - This project is complete for now. The office area will later be completed per tenant's request,

IMG 9243

IMG 9242

IMG 9240

IMG 9236

IMG 9223

IMG 9222

IMG 9220

IMG 9218

IMG 9206

IMG 9186

IMG 9147

IMG 9074

IMG 9028

IMG 9029

IMG 9036

IMG 9037

IMG 9038

IMG 9130

IMG 9138

IMG 9046

IMG 9050

IMG 9069

IMG 9073

IMG 9102

IMG 9108

IMG 9105

IMG 9117

IMG 9099

IMG 9119

IMG 9126

IMG 9085

 

9.05.19 - This project is near completion. Tilt installation is underway then punch-out items will be addressed,

IMG 8504

IMG 8505

IMG 8506

IMG 8508

IMG 8509

IMG 8510

IMG 8511

 

9.03.19 - Crews are painting the breakroom, restrooms, and doors. Lights were installed in the restrooms. M&M Erectors separated hanger doors 3 & 4, then repaired the weatherstrip after the separation,

1

2

5

10

13

14

15

16

20

31

32

 

8.16.19 - Electricians are working on the rolling hangar doors to prep for power. Flooring contractors began work by demoing existing tile in the women's room and by installing wall tiles in the men's room,

3

1

4

2

 

6.03.19 - Electricians are running extra grounding and cad welding to the columns,

9

4

5

8

 

4.29.19 -  Electricians are installing exterior wall lights on the North side of the hangar. Crews continue to paint steel and conduit in the hangar areas. Crewmen are also breaking up the driveway, while A/C work continues in the offices, and blades are being installed on the big fan,

1

3

4

10

14

16

17

22

 

4.24.19 - The doors are complete. Electrical and interior painting continues. This project is near completion,

IMG 3916

IMG 3870

IMG 3880

IMG 3899

4.01.19 - Crewmen continue to trim and sheet the rolling doors, and line the interior hanger walls. Electrical continues as well as interior painting,

IMG 7585

IMG 7588

IMG 7590

IMG 7592

IMG 7593

IMG 7596

3.29.19 - Liner panels are being installed,

IMG 1035

IMG 1036

IMG 1037IMG 1038IMG 1040

3.17.19 - Crewmen poured the door railings and continue to sheet the high roof with insulated roof sheeting. Crewmen are also installing the gutters and downspouts o the west side. Electricians continue hangers and conduit for the high bay lights as interior hangar walls are bing insulated and the gas line is being run in the hangar,

19

23

27

3.11.19 - Crewmen have progressed to sheeting the highest roof and installing the gutters and downspouts. Electrical work continues,

IMG 0870

IMG 0871

IMG 0872

IMG 0873

IMG 0874

IMG 0875

 

2.20.19 - Crewmen continue to sheet the lower roof. Electricians are roughing in the electrical and interior duct work is also underway,

IMG 2718

IMG 2719

IMG 2720

IMG 2721

 

1.21.19 - Crewmen are installing insulaton straps. Plumbers continue to relocate plumbing lines and the interior build out continues,

IMG 0354

IMG 0355

IMG 0356

IMG 0357

1.07.19 - Hanging rafters,

IMG 2601

IMG 2603

 

12.18.18 - Crews began hanging steel last week,

IMG 0055

IMG 0056

IMG 0057

 

 

12.03.18 - The foundation has been saw cut,

IMG 3400

11.29.18 - The foundation was poured this week,

 IMG 0197

IMG 0205

IMG 0717

 

11.19.18 - Crewmen are tying double rebar mat for the foundation,

3

4

5

 

10.21.18 - Crewmen  have drilled 27 of the 32 piers,

13

1

10

14

9.24.18 - Crews are building pad for the foundation,

3

5

6

 

9.07.18 - Site excavation continues,

4

1

2

3

 

8.15.18 - Work began for Wilson Air's new 28,000 SF hangar and office, which is to tie into the hangar we constructed in 2014. Crewmen began breaking up the outside perimeter of slab,

IMG 6308

A

B

6

 

  5888 Hits
5888 Hits