7.06.22 - The pad and utilities are complete. Crews will begin drilling the piers this week,
5.16.22 - Sitework continues,
5.15.22 - The project consists of erecting 4 buildings for the Closner Equipment Co.
The buildings are Office, Warehouse, Repair Bays, and a Wash Bay.
Total is about 6.5 acres with new grading, drainage, and paving plan. Lot will be fenced with automatic gates installed.
Detention pond had 858 cubic yards of dirt removed per the civil engineering plans for the offset of drained water. This portion of the project is complete.
6.02.22 - Crewmen are addressing punch out items and the project will be completed by next week,
5.11.22 - This project is complete. Waiting on power,
3.18.22 - The stucco is complete. The ceiling grid installation is underway, and the electricians are installing the lights,
3.02.22 - Crews have made great progress this month. The paving is complete and masonry has begun. Interior crews continue to hang sheetrock,
2.15.22 - Interior crews are hanging drywall and the concrete crewmen are forming the paving. The excavation of the business park's eastern retention pond is almost complete,
1.19.22 - Erectors are sheeting the roof. Framers are framing the walls.
1.04.22 - Erectors are hanging steel for this new facility,
12.16.21 - Crews are preparing for the foundation pour,
11.11.21 - Site work is underway for a new 20,000 SF trade school, located at 20213 Binford Rd,
6.02.22 - Power was turned on today, allowing the remaining trades to finish their work,
3.03.22 - Interior build out continues. Windows are installed,
2.08.22 - The building is sheeted. Erectors are installing the ridge vents. Framers have completed framing the office walls.
12.22.21 - The foundation was poured today,
7/01/21 - This new 8,600 SF office and warehouse is in permitting. Construction updates will be available on this page, so check back for this location's progress and availablility.
6.02.22 - Power was turned on today. Flooring and the ceiling tile installation will follow,
3.03.22 - Interior framing is underway,
2.08.22 - Erectors began hanging the steel today,
7/01/21 - This new 8,600 SF office and warehouse is in permitting. Construction updates will be available on this page, so check back for this location's progress and availablility.
5.20.22 - Crewmen are pouring the offsite parking lot today,
5.11.22 - Crewmen are forming for the offsite parking lot. The next phases include a warehouse building and paving in the main yard,
This project includes two ground-up spec office/warehouses totaling 43,000 SF. Scope of project also includes extending the business park's private drive and utilities.
3.02.22 - Buildings 4 and 8 are completed,
2.18.22 - Wrapping up work on Buildings 4 and 8,
12.29.21 - Stucco and masonry to begin. Landscaping continues for Bldg 4 and began today for Bldg 8. Electricians are digging up the underground conduit to AT&T's conduit at both bldgs,
12.23.21 - Ceiling tile installation continues for Buildings 4 & 8, fixtures are installed in both buildings, receptacles and can lights are going in today in both buildings, and crews are hooking up the condenser units for Buildings 4 and 8,
12.16.21 - Flooring continues,
11.05.21 - Waiting on one piece of glass to be installed above the door on Building 8. Plumbers are ready for fixtures as soon as the floors are installed. Electrial work continues for both buildings.
10.29.21 - The OH door installation continues for Building 8. Plumbers are also installing the water heater and pipe for Building 8. Electricians continue their work on Buildings 4 and 8,
10.22.21 - Crews cleaned and backfilled around the seven new concrete drainage flumes. Crews are installing lights and ceiling grid in Buildng 4. Waiitng on AC materials for buildings 4 and 8,
9.07.21 - Northwinds crewmen are working to back fill the south side of Bldg 8, next to the drainage ditch, and dress it up. M&M Erectors continue the wall panel installation on Bldg 4,
8.24.21 - Erectors are lifting Bldg #4's roof,
8.18.21 - Paving was poured for Bldg #8. Erectors are lifting Bldg #4,
7.24.21 - Foundation was poured this morning for Bldg #4,
7.02.21 - Crewmen continue to lay out the sub-sub grade in the paving areas around Bldg. 4 & 8, and are cutting to grade to prepare for select fill,
6.25.21 - We are resuming select fill in the paving areas around pad #8. Cutting the paving sub grade in the west end of pad #4 to be able to get a minimum of 8” of select fill and compacted. Plumbers are backfilling trenches.
6.12.21 - Windrowing the select fill on Pad 4 and on Pad 8 to help pull the moisture out. Regrading and compacting to get ready for their test on Monday morning. Working on the ditch on the north side of BLDG. 8. Shaping and grading to drain to the pond inlet.
6.11.21 - Site crewmen are laying down the select fill that was stock piled yesterday on Pad 4 and began laying down the select fill that was stock piled yesterday on Pad 4. Crews started the first lift on pad 8, compacting in lifts. The plumbers continue working on the 8” water tie in and continued digging their trench.
6.10.21 - Site crewmen began the select fill in Pad 4 and are compacting in lifts.
6.09.21 - Crews are cutting bldg. pad 4 & 8 to sub grade (in preparation for select fill). Running the 324 over pad 8 to compact it. Back filling stabilized. Back filling stabilized sand over the 2 culverts. Began the layout and grading on the north side ditch,
6.08.21 - Cutting bldg. pad 4 to sub grade and starting on pad 8 to prepare for select fill. Running the Roller and 324 over pad 4 to compact it.
6.07.21 - Starting the 24” & 15” coverts - excavating to grade, building up hdpe bed with stabilized sand, laying the pipe and back fill to 6” from top of pipe for city inspections. Cutting bldg. pad #4 to sub grade to prepare for select fill.
1.26.22 - This was such a fun project. Below are final photos of their new church,
11.20.21 - This project is nearing completion. Floor installation is underway, as interior painting continues. Start-up crewmen are installing AC units. The final clean and completion are scheduled for next week,
11.10.21 - Electricians are tieing in homeruns and pulling wire into the sanctuary, bathroom tile installation continues, and masons continue bricking the exterior. Erectors began trimming the building and plumbers set 5 septic tanks,
10.19.20 - The ceiling grid is installed and door frames are being installed,
10.15.21 - The electricians are pulling wire as additional crews clean the site and reset the silt fence. The data wire is also being run.
9.12.21 - The glass is installed. Drywall, electrical, and HVAC work continue,
9.02.21 - Framers are hanging drywall. HVAC crewmen are hanging the ductwork,
8.24.21 - The exterior walls are up and interior framing and buildout are underway,
8.04.21 - Erectors have progressed to hanging the pre-assembled roof sections,
8.02.21 - Erectors are into their second day hanging steel,
7.23.21 - The foundation is cured and saw cut. Steel delivery is scheduled for tomorrow,
7.22.21 - Crews began pouring the foundation for the church building this morning,
7.01.21 - Crews laid out form boards, and finished digging grade beams. Electricians are working on underground electrical for the foundation.
6.30.21 - Electricians are laying out the underground electrical,
6.26.21 - The plumbers continue underground plumbing,
6.24.21 - Underground plumbing continues,
6.22.21 - Crewmen cleared shrubs along the drive for the future sign. Additional crews spread lime to speed the drying time of the job site, and laid out grade beam locations,
6.18.21 - Crewmen drilled and poured piers. Electricians installed conduit for light poles.
5.14.21 - Curbs were poured for the parking area and have cured,
4.27.21 - Crewmen are pouring the parking areas today,
3.16.21 - Crewmen continue their work on the pond outfall, digging out the second box, with stabilization, rest box and pipe, backfill, and dress up,
1.12.21 - Site crewmen continue excavating the detention pond and grading the site,
12.23.20 - Crews are clearing the site to prepare for the church's building pad,
Sitework will soon begin for Connect Church's new 12,000 SF facility. The new church facility will include a sactuary, class rooms, and administrative offices,
8.24.21 - The sidewalk extension is complete for the Word of God Christian Fellowship Church congregation,
7.16.21 - Photos of the completed project,
6.25.21 - Crews finished addressing the punch out items for this project.
6.23.21 - Hanging generator enclosure doors and painting.
6.04.21 - Prepping for Generator pad pour,
6.02.21 - Electrical final called in for tomorrow.
6.01.21 - Started dropping ceiling tile and began final clean. Fire Marshall performed visual and hydro test. Approved to cover ceiling.
5.29.21 - Electricians are hanging lights, hanging new exterior wall packs
5.26.21 - Passed ADA inspection. Restroom stall doors are hung with hardware installed,
5.25.21 - Flooring crews are setting core base and addressing punch items. Fire Marshall visual is scheduled for June 1st. Furniture delivery is scheduled for June 7th.
5.24.21 - Electricians are labeling and tracing circuits. Concrete crew in to form and pour lab trough.
5.20.21 - Painters are painting out the walls. Plumber added a check valve on the circulating line. Electricians installed wiremold and plates.
5.19.21 - Crews are setting all window blinds. Painters are painting out all walls.
5.17.21 - Restroom mirrors are installed. Bad gaskets have been relaced on exterior windows. Glass sidelites are set. Electricians are setting devices. Painters are applying final coat.
5.14.21 - Crews are installing lavatories in break room and the copy room. Plumbers are finishing their fixture installations. Electricians are setting two fixtures in the restrooms,
5.04.21 - Electricians are tying in the lights. Sprinkler heads are being installed. Tile installation is underway in the restrooms and front store wall. Carpet is being installed on the West side.
5.03.21 - HVAC removed the existing rooftop units (RTUs) and set new RTUs. They also ran condensate lines, insulated vav's and copper linesets. Electricials set light fixtures and dropped whips into fixtures, and set pub panels in the electrical room. Fire sprinklers are being installed on grid, and the ceramic tile is being installed in the restrooms, and west office areas. The roofers started cricket on the North side, and are repairing the roof areas in the NE corner,
4.28.21 - Plumbing and Electrical rough-in are complete. Walls are taped and floated. Drywall crew are installing the ceiling grid. IT contractor is running data cabling,
3.16.21 - Crewmen began hanging duct work, and are saw cutting areas of slab to be removed for plumbing and electrical,
3.11.21 - This project includes remodeling 9,188 SF of office, 273 SF of lab space, and 679 SF of warehouse.
4.20.21 - The rock and concrete work are completed. Fence installation and clean up remain.
4.05.21 - Crewmen continue cutting grade,
3.26.21 - Site crew began scraping for a new rock yard at 4121 Katy Hockley Rd. This is part of the new tenant’s improvemnets,
2.06.20 - This project is complete,
12.15.19 - The building is fully trimmed. Flooring began in the entry,
12.03.19 - Painting is complete and flooring will soon follow,
10.05.19 - Sheeting is underway,
9.27.19 - Parking lot is poured. Erectors are hanging steel,
9.24.19 - Crews are erecting the building. More paving has been poured,
9.12.19 - The building pad was poured and crews are forming for additional paving,
7.16.19 - Crews are pouring the main drive,
7.11.19 - Crewmen began building the pad and laying out the private road for the business park,
6.28.19 - Sitework is underway for this new 9,300 SF office/warehouse, located off Katy Hockley Road and Clay Road. This new facility is available for Sale or Lease,
12.29.20 - This project was completed on Dec 2nd, with the exception of a few small items that are being wrapped up,
9.15.20 - Painters started applying the first coat of paint, and Site crewmen are making the final grade,
8.24.20 - Northwinds crewmen are laying base for an asphalt parking lot. Over the next two weeks, they will final grade around the building and prepare for the landscaping installation. The interior buildout continues.
7.07.20 - Erectors continue to hang steel,
6.19.20 - The building was delivered.
6.17.20 - Crews are pouring the building pad,
6.10.20 - Site crewmen have completed the pad. Concrete crews began digging beams. Electricians are running service conduit,
12.27.19 - This project calls for a 9,500 SF Freestanding office and control center. The project is located in Midstream's existing terminal, on the East side of Houston. We are currently in the planning and permitting stage of this project.
12.22.20 - Crewmen are painting stripes and joint sealing in the NW paving area. Crewmen are also removing existing parking stripes.
12.18.20 - Crews are painting stripes and joint sealing in SE paving area only.
12.07.20 - Crews are dewatering the site, spreading spoils, and loading materials and cleaning equipment.
11.20.20 - The NE paving pour is underway,
11.14.20 - Storm work continues,
11.11.20 - Crewmen are laying storm,
11.10.20 -
11.05.20 - Crews began pouring the paving this morning,
12.11.20 - Crewmen are to hydroseed the areas surrounding the new paving, and install new light poles,
11.24.20 - The parking lot expansion is complete, just in time for FedEx's holiday rush season. Crews are back filing and sweeping,
11.17.20- Pour #1 of the south parking is complete. Crews are tying steel for Friday's pour,
11.10.20 - Crewmen are installing the catch basin, and setting forms for the south parking lot,
10.27.20 - Site crew continue the mass grading for the south parking lot expansion.
10.19.20 - Site crew began scraping and excavating for a 2.5-acre parking lot expansion,
8.21.20 - This project is near completion,
7.27.20 - Crewmen are painting the plywood walls in 115 & 119, installing hardware on doors and starting the ceiling tile installation. Flooring crews have completed the VCT and cove base throughout Duncan's office areas. Electrical is complete and ready for inspection. Once the canopy is trimmed out, the remaining lighting will be completed,
7.20.20 - Interior painting continues. Electricians continue above-ceiling rough in and wiring of the electrical panels.
7.02.20 - Crewmen continue to run the ceiling grid and duct work. Electrical rough in has begun.
6.30.20 - Crews are running wall angle and hanging ceiling wires. They started running the ceiling grid. Crewmen are adding fire-rated plywood at the TV locations. AC contractor continues running hangers and assembling the AC ducts.
6.28.20 - This project calls for a 4,231 SF interior build out of an existing shell building (SR-8), that we constructed in 2019. Metal stud framing is underway. The Fire subcontractor began bringing the pipe drops to 1'-0" above the ceiling height.
8.14.20 - This project is complete,
8.06.20 - Final clean is scheduled for next week,
7.07.20 - Waiting on power,
6.12.20 - Irrigation installation is underway. The crane installation is complete. Once this project has final power, crews will complete the AC, flooring, MEP trim out, and interior office painting,
5.29.20 - The entrance canopy is installed,
5.28.20 - Stone is complete and the interior walls are two sided, taped, and floated. AC grills will be completed today,
4.21.20 - Walls and roof are sheeted. The overhead doors are being installed, and the office framing, AC work, and plumbing rough in has begun,
4.13.20 - The building is 60% complete. Crewmen started to frame the office. Paving and curbs are completed,
3.30.20 - Erectors continue to hang steel as additional crews prepare for next weeks pour,
3.25.20 - Erectors are unloading steel,
3.18.20 - The foundation was poured today,
3.13.20 - Plumbing and electrical groundout are waiting on inspections. Crews are digging grade beams and seting steel, preparing to pour next Wednesday,
3.11.20 - Crews are setting p the slab for next week's pour. Crews are also plumbing ground out for the fire line,
3.02.20 - Finishing up subgrade for paving. Steel has been delivered,
2.20.20 - Crews finished installing the storm and will continue to form the pad,
12.27.19 - Crews have begun sitework for Grizzly's new facility. Dennis Montesinos is the PM and Kenneth Whitmill is the Superintendent,
7.06.20 - We submitted the As-built certificates and are waiting for the final inspection. Centerpoint was onsite last week to set markers for the electrical service poles, for the lift station.
6.17.20 - Engs As-built inspection took place today. Once we receive the Engs As-built certificate, we can submit to Harris Co flood control and request final inspections for power release,
5.28.20 - Crewmen are pumping water to finish the storm water lift station.
5.11.20 - Rock yard is complete. Retention ponds are dry and final graded. Installing the last of the storm pipe lift station.
4.15.20 - Laying flex base for rock yard. Completing final dress up of retention ponds.
3.09.20 - Crewmen are cutting grades on the detention pond and storm swale,
3.02.20 - The pond is dried and crews are cutting grades,
2.21.20 - Crewmen continue to work on the pond. Grades have been cut and the storm as been installed.
12.30.19 - Dennis Montesinos will soon oversee this project in Cypress, which calls for a two-acre rock yard.
Completed project photos,
6.08.20 - Painting is near completion. This project will be completed next week, following landscaping,
5.07.20 - Masonry contractors completed the stucco. The wall tile in the restrooms is being installed. M&M Erectors are trimming the building and installing the entry canopy,
4.30.20 - Painters completed their work painting the walls and ceilings. Door frames are being installed. The masonry contractor began the stucco facade,
4.23.20 - The entry canopy is complete. Painters are spraying the exposured structure. Electricians are building the service panels,
4.14.20 - AVAdek is installing the entry pergola. HVAC ductwork is being installed. Electricians are roughing in the plugs and switches,
4.02.20 - Interior buildout continues, window and door installation are also underway,
3.10.20 - Roof sheeting and siding are underway,
3.02.20 - Crewmen have finished sheeting the east wall,
2.27.20 - Erectors continue to hang steel, and began sheeting the east wall,
2.20.20 - The building is delivered and the erectors are shaking out and assembling the steel,
2.15.20 - Crews are pouring the foundation,
2.11.20 - Crews are prepping for the foundation pour,
12.14.19 - Crewmen plan to pour paving on Monday,
12.12.19 - Site work continues,
Crewmen will soon begin constructing a new 8,000 SF office building for E Squared Marine,
4.08.20 - The facility's signs were installed on Friday. This project was completed.
3.24.20 - The warehouse is being swept. Windows are being cleaned. This project is nearing completion,
3.09.20 - Lights are on. Landscaping and painting are underway. Flooring will soon follow,
2.21.20 - Painters are working on the offices. Cabinets, flooring, and landscaping are being installed,
1.17.20 - Crews are moving along with the interior buildout,
12.30.19 - Erectors are trimming the facility and finishing the canopies. Interior buildout continues with electrical, framing, and drywall,
12.04.19 - Erectors have one final section of roof to sheet. Crewmen continue to build out the interior as site crewmen prepare for the next paving pours,
11.15.19 - Exterior painting is underway and Erectors continue to sheet the roof. HVAC and interior framing is also underway,
10.28.19 - Erectors are sheeting the office side of the facility and will continue to hang roof sections tomorrow. The sprinkler system is being installed and crews are framing for the next paving pour,
10.01.19 - Crewmen are sheeting the roof,
9.13.19 - Crewmen are running the purlin straps, rubbing out the tilt-wall panels, welding the inbeds, and forming for Monday's paving pour,
9.05.19 - The roof system is going up. The truck ramp is poured and Building G's grade beam was poured. The surveyer also began laying out the parking for crewmen to later form,
8.27.19 - Steel is being assembled and erected,
8.20.19 - Crews are lifting the tilt-wall panels,
7.24.19 - Crews continue to prep the site for the next pour,
7.12.19 - Crews began pouring the pad,
7.09.19 - Crews are making up the slab in preparation for Phase 1 of the foundation pour, scheduled for Friday,
6.27.19 - Crewmen are dewatering so they can re-frame the pad,
6.17.19 - Electrical and Plumbing underground are underway. Crews are framing up the pad for the first pour.
6.03.19 - The building pad is 95% complete,
4.29.19 - The storm sewer is complete. The building pad has one lift, with two more to go,
4.09.19 - Crewmen are laying the storm on the North end. The building pad is 90% to start of fill elevation. The fire line and fire hydrant are set and approved by the fire marshall, and the domestic water tap and meter are set,
3.25.19 - Crews have completed the Stom on the South end, with the exception of tying into the downspout drains. Crews have hauled in 26 loads to tighten the SE corner of the building pad. The Storm on the East and NE side of the building is complete,
3.22.19 - Crews continue the mass grading and have laid approximately half of the strom drainage pipe,
3.11.19 - Storm on the south end is complete. Bringing in select fill for pad,
2.27.19 - The brush grinding is complete. The storm on the south end is tied into the street inlet. South storm is 75% complete. Crewmen dug ditches around the building pad area to help release trapped water, and to more quickly dry the areas of saturated soils,
2.16.19 - Crews are installing the storm sewer and dewatering the site,
1.10.19 - Crewmen began clearing trees,
12.27.18 - Silt fencing is installed.
12.17.18 - Excavation is scheduled to begin in January.