12.29.20 - This project was completed on Dec 2nd, with the exception of a few small items that are being wrapped up,
9.15.20 - Painters started applying the first coat of paint, and Site crewmen are making the final grade,
8.24.20 - Northwinds crewmen are laying base for an asphalt parking lot. Over the next two weeks, they will final grade around the building and prepare for the landscaping installation. The interior buildout continues.
7.07.20 - Erectors continue to hang steel,
6.19.20 - The building was delivered.
6.17.20 - Crews are pouring the building pad,
6.10.20 - Site crewmen have completed the pad. Concrete crews began digging beams. Electricians are running service conduit,
12.27.19 - This project calls for a 9,500 SF Freestanding office and control center. The project is located in Midstream's existing terminal, on the East side of Houston. We are currently in the planning and permitting stage of this project.
12.22.20 - Crewmen are painting stripes and joint sealing in the NW paving area. Crewmen are also removing existing parking stripes.
12.18.20 - Crews are painting stripes and joint sealing in SE paving area only.
12.07.20 - Crews are dewatering the site, spreading spoils, and loading materials and cleaning equipment.
11.20.20 - The NE paving pour is underway,
11.14.20 - Storm work continues,
11.11.20 - Crewmen are laying storm,
11.10.20 -
11.05.20 - Crews began pouring the paving this morning,
12.11.20 - Crewmen are to hydroseed the areas surrounding the new paving, and install new light poles,
11.24.20 - The parking lot expansion is complete, just in time for FedEx's holiday rush season. Crews are back filing and sweeping,
11.17.20- Pour #1 of the south parking is complete. Crews are tying steel for Friday's pour,
11.10.20 - Crewmen are installing the catch basin, and setting forms for the south parking lot,
10.27.20 - Site crew continue the mass grading for the south parking lot expansion.
10.19.20 - Site crew began scraping and excavating for a 2.5-acre parking lot expansion,
8.21.20 - This project is near completion,
7.27.20 - Crewmen are painting the plywood walls in 115 & 119, installing hardware on doors and starting the ceiling tile installation. Flooring crews have completed the VCT and cove base throughout Duncan's office areas. Electrical is complete and ready for inspection. Once the canopy is trimmed out, the remaining lighting will be completed,
7.20.20 - Interior painting continues. Electricians continue above-ceiling rough in and wiring of the electrical panels.
7.02.20 - Crewmen continue to run the ceiling grid and duct work. Electrical rough in has begun.
6.30.20 - Crews are running wall angle and hanging ceiling wires. They started running the ceiling grid. Crewmen are adding fire-rated plywood at the TV locations. AC contractor continues running hangers and assembling the AC ducts.
6.28.20 - This project calls for a 4,231 SF interior build out of an existing shell building (SR-8), that we constructed in 2019. Metal stud framing is underway. The Fire subcontractor began bringing the pipe drops to 1'-0" above the ceiling height.
8.14.20 - This project is complete,
8.06.20 - Final clean is scheduled for next week,
7.07.20 - Waiting on power,
6.12.20 - Irrigation installation is underway. The crane installation is complete. Once this project has final power, crews will complete the AC, flooring, MEP trim out, and interior office painting,
5.29.20 - The entrance canopy is installed,
5.28.20 - Stone is complete and the interior walls are two sided, taped, and floated. AC grills will be completed today,
4.21.20 - Walls and roof are sheeted. The overhead doors are being installed, and the office framing, AC work, and plumbing rough in has begun,
4.13.20 - The building is 60% complete. Crewmen started to frame the office. Paving and curbs are completed,
3.30.20 - Erectors continue to hang steel as additional crews prepare for next weeks pour,
3.25.20 - Erectors are unloading steel,
3.18.20 - The foundation was poured today,
3.13.20 - Plumbing and electrical groundout are waiting on inspections. Crews are digging grade beams and seting steel, preparing to pour next Wednesday,
3.11.20 - Crews are setting p the slab for next week's pour. Crews are also plumbing ground out for the fire line,
3.02.20 - Finishing up subgrade for paving. Steel has been delivered,
2.20.20 - Crews finished installing the storm and will continue to form the pad,
12.27.19 - Crews have begun sitework for Grizzly's new facility. Dennis Montesinos is the PM and Kenneth Whitmill is the Superintendent,
7.06.20 - We submitted the As-built certificates and are waiting for the final inspection. Centerpoint was onsite last week to set markers for the electrical service poles, for the lift station.
6.17.20 - Engs As-built inspection took place today. Once we receive the Engs As-built certificate, we can submit to Harris Co flood control and request final inspections for power release,
5.28.20 - Crewmen are pumping water to finish the storm water lift station.
5.11.20 - Rock yard is complete. Retention ponds are dry and final graded. Installing the last of the storm pipe lift station.
4.15.20 - Laying flex base for rock yard. Completing final dress up of retention ponds.
3.09.20 - Crewmen are cutting grades on the detention pond and storm swale,
3.02.20 - The pond is dried and crews are cutting grades,
2.21.20 - Crewmen continue to work on the pond. Grades have been cut and the storm as been installed.
12.30.19 - Dennis Montesinos will soon oversee this project in Cypress, which calls for a two-acre rock yard.
Completed project photos,
6.08.20 - Painting is near completion. This project will be completed next week, following landscaping,
5.07.20 - Masonry contractors completed the stucco. The wall tile in the restrooms is being installed. M&M Erectors are trimming the building and installing the entry canopy,
4.30.20 - Painters completed their work painting the walls and ceilings. Door frames are being installed. The masonry contractor began the stucco facade,
4.23.20 - The entry canopy is complete. Painters are spraying the exposured structure. Electricians are building the service panels,
4.14.20 - AVAdek is installing the entry pergola. HVAC ductwork is being installed. Electricians are roughing in the plugs and switches,
4.02.20 - Interior buildout continues, window and door installation are also underway,
3.10.20 - Roof sheeting and siding are underway,
3.02.20 - Crewmen have finished sheeting the east wall,
2.27.20 - Erectors continue to hang steel, and began sheeting the east wall,
2.20.20 - The building is delivered and the erectors are shaking out and assembling the steel,
2.15.20 - Crews are pouring the foundation,
2.11.20 - Crews are prepping for the foundation pour,
12.14.19 - Crewmen plan to pour paving on Monday,
12.12.19 - Site work continues,
Crewmen will soon begin constructing a new 8,000 SF office building for E Squared Marine,
4.08.20 - The facility's signs were installed on Friday. This project was completed.
3.24.20 - The warehouse is being swept. Windows are being cleaned. This project is nearing completion,
3.09.20 - Lights are on. Landscaping and painting are underway. Flooring will soon follow,
2.21.20 - Painters are working on the offices. Cabinets, flooring, and landscaping are being installed,
1.17.20 - Crews are moving along with the interior buildout,
12.30.19 - Erectors are trimming the facility and finishing the canopies. Interior buildout continues with electrical, framing, and drywall,
12.04.19 - Erectors have one final section of roof to sheet. Crewmen continue to build out the interior as site crewmen prepare for the next paving pours,
11.15.19 - Exterior painting is underway and Erectors continue to sheet the roof. HVAC and interior framing is also underway,
10.28.19 - Erectors are sheeting the office side of the facility and will continue to hang roof sections tomorrow. The sprinkler system is being installed and crews are framing for the next paving pour,
10.01.19 - Crewmen are sheeting the roof,
9.13.19 - Crewmen are running the purlin straps, rubbing out the tilt-wall panels, welding the inbeds, and forming for Monday's paving pour,
9.05.19 - The roof system is going up. The truck ramp is poured and Building G's grade beam was poured. The surveyer also began laying out the parking for crewmen to later form,
8.27.19 - Steel is being assembled and erected,
8.20.19 - Crews are lifting the tilt-wall panels,
7.24.19 - Crews continue to prep the site for the next pour,
7.12.19 - Crews began pouring the pad,
7.09.19 - Crews are making up the slab in preparation for Phase 1 of the foundation pour, scheduled for Friday,
6.27.19 - Crewmen are dewatering so they can re-frame the pad,
6.17.19 - Electrical and Plumbing underground are underway. Crews are framing up the pad for the first pour.
6.03.19 - The building pad is 95% complete,
4.29.19 - The storm sewer is complete. The building pad has one lift, with two more to go,
4.09.19 - Crewmen are laying the storm on the North end. The building pad is 90% to start of fill elevation. The fire line and fire hydrant are set and approved by the fire marshall, and the domestic water tap and meter are set,
3.25.19 - Crews have completed the Stom on the South end, with the exception of tying into the downspout drains. Crews have hauled in 26 loads to tighten the SE corner of the building pad. The Storm on the East and NE side of the building is complete,
3.22.19 - Crews continue the mass grading and have laid approximately half of the strom drainage pipe,
3.11.19 - Storm on the south end is complete. Bringing in select fill for pad,
2.27.19 - The brush grinding is complete. The storm on the south end is tied into the street inlet. South storm is 75% complete. Crewmen dug ditches around the building pad area to help release trapped water, and to more quickly dry the areas of saturated soils,
2.16.19 - Crews are installing the storm sewer and dewatering the site,
1.10.19 - Crewmen began clearing trees,
12.27.18 - Silt fencing is installed.
12.17.18 - Excavation is scheduled to begin in January.
12.15.19 - This property Available for Sale or Lease. Call for more information, 713-671-5300.
12.03.19 - Below are photos of the final interior,
10.05.19 - Landscaping is complete and flooring is near completion,
9.27.19 - Power has been set on the building. Landscaping is being installed. Next week the ceiling tiles and flooring will be installed,
9.13.19 - Flooring and landscape installation are underway,
8.09.19 - Electricians continue to run lights in the warehouse, while plumbers work on the waterline. Painting is underway. M&M Erectors finished trimming out the building,
7.11.19 - Masons are laying the stone. Interior crews are framing the walls. Septic tanks are being installed,
6.28.19 - This office/warehouse is now fully sheeted. Interior framing is underway, as additional crewmen frame for the next paving pours, and the erectors trim the facility,
6.06.19 - Erectors have progressed to installing the wall and skylight sheeting,
3.25.19 - Crews poured the front paving last week,
3.20.19 - Driveway is poured and the pad is complete. Concrete crews will be pouring the front half of the paving tomorrow,
12.09.19 - This project was completed in November and SiteOne is moving in,
10.14.19 - Interior painting is underway and landscaping installation will soon follow,
9.27.19 - Painters are wrapping up. Site crew is cleaning up the site. The building should have power next week,
9.09.19 - Crews are tying steel in preparation for Wednesday's paving pour,
8.19.19 - The building is fully sheeted and trimmed. Downspouts are installed and the side canopy. Interior framing is underway,
8.09.19 - M&M Erectors continue to sheet the roof. Site crewmen are grading for paving,
7.23.19 - Crewmen are erecting the building,
7.10.19 - Crews are tying steel for tomorrow morning's pour,
6.28.19 - Sitework continues,
6.26.19 - Crews broke ground on this project last week. It will be a new 7,000 SF retail center and showroom for a wholesale landscape and irrigation supplier SiteOne. Trevor Robinson is the PM.
10.15.19 - This project is complete for now. The office area will later be completed per tenant's request,
9.05.19 - This project is near completion. Tilt installation is underway then punch-out items will be addressed,
9.03.19 - Crews are painting the breakroom, restrooms, and doors. Lights were installed in the restrooms. M&M Erectors separated hanger doors 3 & 4, then repaired the weatherstrip after the separation,
8.16.19 - Electricians are working on the rolling hangar doors to prep for power. Flooring contractors began work by demoing existing tile in the women's room and by installing wall tiles in the men's room,
6.03.19 - Electricians are running extra grounding and cad welding to the columns,
4.29.19 - Electricians are installing exterior wall lights on the North side of the hangar. Crews continue to paint steel and conduit in the hangar areas. Crewmen are also breaking up the driveway, while A/C work continues in the offices, and blades are being installed on the big fan,
4.24.19 - The doors are complete. Electrical and interior painting continues. This project is near completion,
4.01.19 - Crewmen continue to trim and sheet the rolling doors, and line the interior hanger walls. Electrical continues as well as interior painting,
3.29.19 - Liner panels are being installed,
3.17.19 - Crewmen poured the door railings and continue to sheet the high roof with insulated roof sheeting. Crewmen are also installing the gutters and downspouts o the west side. Electricians continue hangers and conduit for the high bay lights as interior hangar walls are bing insulated and the gas line is being run in the hangar,
3.11.19 - Crewmen have progressed to sheeting the highest roof and installing the gutters and downspouts. Electrical work continues,
2.20.19 - Crewmen continue to sheet the lower roof. Electricians are roughing in the electrical and interior duct work is also underway,
1.21.19 - Crewmen are installing insulaton straps. Plumbers continue to relocate plumbing lines and the interior build out continues,
1.07.19 - Hanging rafters,
12.18.18 - Crews began hanging steel last week,
12.03.18 - The foundation has been saw cut,
11.29.18 - The foundation was poured this week,
11.19.18 - Crewmen are tying double rebar mat for the foundation,
10.21.18 - Crewmen have drilled 27 of the 32 piers,
9.24.18 - Crews are building pad for the foundation,
9.07.18 - Site excavation continues,
8.15.18 - Work began for Wilson Air's new 28,000 SF hangar and office, which is to tie into the hangar we constructed in 2014. Crewmen began breaking up the outside perimeter of slab,
10.10.19 - Subway will open next weekend. Below are final photos of this project. Final photos of Joe's Burgers are below Subway. Joe's Burgers will open this weekend,
Joe's Burgers,
10.02.19 - A final clean is underway for Subway,
10.01.19 - Joe's Burgers is complete,
9.24.19 - Joe's Burgers will be complete after the fire inspection and crewmen will wrap up their work on Subway at the end of the week,
8.21.19 - Crews began installing the stainless steel countertops and pass through window at Joe's Burgers,
Subway - Crews continue to install the metal facade and the vent hood,
8.20.19 - Electricians are building the service at Joe's Burgers. The galvanized pipe ceiling treatment is being hung and the kitchen equipment has arrived and is getting installed,
Subway - Metal facade is being installed. Electricians are hanging the pendant fixtures in the dining area. Kitchen wall tile installation is also underway.
8.09.19 - Crews are applying epoxy flooring in the kitchen area of Joe's Burgers, while M&M crewmen install the framing for canopies and the roof for the wash bay. Finishers are taping and floating at Subway. FRP is being installed in the kitchen. Electricians are running conduit,
7.29.19 - Paving and tile work are complete for Joe's Burgers,
7.08.19 - Masons continue to lay the brick as Carpenters install the ceiling treatments for Joe's Burgers. Roofers are installing curbs and electricians are roughing in the lights and switches at Subway.
Subway,
6.27.19 - Spiral ductwork is complete for Joe's Burgers. Vent-a-hood is installed. Masons started the brickwork.
6.25.19 - Window frames are installed and the roof is complete for Joe's Burgers. Electricians are roughing in the electrical, while HVAC contractors hang the spiral ductwork. --The block and water proofing is complete for Subway. Curbs are set and roofers began installing the iso board,
6.07.19 - Crewmen are installing hat channels for Joe's Burgers, and hanging steel for Subway,
6.03.19 - Crews have been addressing the CMU installation, setting embedded plates for the bar joists, and filling walls with concrete. As for Joe's Burgers, crewmen are laying out the roof curbs for the AC and vents, cutting AC access and welding angle supports, framing, and pouring interior curbs. Electrical rough-in is also underway.
5.29.19 - Crewmen began CMU installation for the Subway restaurant, which will be completed by the end of this week. We expect steel for this building to be delivered on 5/31, and will begin erecting.
Steel erecting is complete and inspected for Joe's Burgers. The roof deck is on and framing has begun. Crewmen plan to pour interior curbs and block outs this week, so framing and plywood can be completed.
5.06.19 - Erectors began hanging steel and the masons continue to build the CMU walls,
4.29.19 - . Joes slab was poured last week. Cmu install is scheduled to start today. As for Subway, crewmen were able to pour beams and prep for the slab pour. Subway's slab pour is scheduled for today and tomorrow.
4.03.19 - Underground is complete. Crews are digging beams and tying steel in preparation for next week's concrete pour,
3.25.19 - Crews are pouring piers today for Joe's Burgers. Plumbers ran the utilities for Subway and are backfilling today,
3.20.19 - The existing slabs are removed. Plumbers have made the utility connections and the boring for the fire main is complete. Concrete crews began tying steel for the piers.
3.17.19 - Crewmen ran utilities and poured trench for Joe's Burgers, and finished removing the slab for Subway,
3.08.19 - Crewmen are saw cutting and breaking out existing slabs, making tie-ins for water, sewer, and gas.
Parking lot expansion is complete,
12.21.18 - Fire inspection is underway,
12.20.18 - Final clean is complete. MUD District inspection is tomorrow, and the final fire inspection is Friday,
12.14.18 - This project is nearing completion. A final clean is scheduled for next week,
11.01.18 - Lights on and painters are applying final coat of paint,
10.30.18 - Lighting is complete. Crewmen are finishing the second coat of paint in the sanctuary,
9.12.18 - Crewmen are sheetrocking walls while Electricians rough in lighting,
8.13.18 - Electricians are roughing in the electrical, Mechanical contractors are installing ductwork, Finishers are taping and floating sheetrock, and M&M crewmen are installing the soffit and trim,
7.20.18 - Masonry and roof sheeting are underway. Crewmen are also framing the interior walls. Flatwork is 80% complete,
7.11.18 - Wall sheeting continues,
7.03.18 - Crewmen are forming up for aditional paving and installing additional purlins. Sheeting continues,
6.28.18 - Crewmen are pouring the first phase of paving this morning,
6.25.18 - Crewmen are forming up paving. Wall sheeting has begun,
6.18.18 - Progress erecting the church building,
6.13.18 - The building and detention lift station arrived,
6.11.18 - Flat work will begin in next few days,
5.30.18 - The foundation pour is underway this morning,
5.23.18 - Storm pipe installation, foundation ground out and forms,
5.11.18 - Crewmen are drilling and pouring foundation piers today,
4.25.18 - The big pond is 75% complete and the pad is 3" above final grade. Waiting on final compaction test today.
4.02.18 - Crews began excavating the detention ponds and continue to dewater the site,
3.23.18 - The site has been stripped of parking area,
5.20.17 - Today we celebrated at a ground-breaking ceremony for the Word of God Church. Construction will soon begin for their new place of worship.
This facility was purchased by Stillo Construction.
11.01.18 - The building is complete. Parking lot cleaning and striping to follow,
9.12.18 - Masons are installing the cast stone. Grid for the acoustical ceiling is being installed,
8.30.18 - Masonry work is underway as crewmen address HVAC and interior framing,
7.20.18 - Crewmen are installing exterior sheathing and are framing interior walls,
7.16.18 - Crewmen have progressed to roof sheeting,
7.06.18 - Crewmen continue to sheet the walls,
7.03.18 - All steel is hung and crewmen have progressed to sheeting the building,
6.25.18 - Crewmen began hanging steel,
5.01.18 - Paving is poured and sawcut. Crewmen begin seeding the detention pond,
4.26.18 - Crewmen poured the paving this morning,
4.12.18 - Crewmen are setting the storm for Spec Bldg 1. Electricians are trimming out electrical service panel for pond lift station and water well,
3.28.18 - Crewmen poured the foundation this morning,
3.23.18 - Excavation of the detention pond is complete. Slab is made up and ready to pour,
3.13.18 - Progress on the water tank and the detention pond,
1.09.18 - The pad is built for this new facility and crewmen are grading the detention pond. This new office/warehouse is Available for Sale or Lease, off Clay Rd in Katy,
This project is complete,
5.04.18 - Waiting on fire marshall approval and final clean.
4.02.18 - Waiting on fire marshal approval.
3.23.18 - Landscaping is underway. The building is complete. Addressing punch out items, cleaning up site, and waiting for power,
1.25.18 - Pouring retaining walls,
1.08.18 - Crewmen are currently taping and floating,
12.13.17 - Crews poured paving this morning,
10.30.17 - Building is sheeted and interior framing underway,
10.25.17 - Sheeting continues,
10.15.17 - Crewmen are hanging steel,
10.06.17 - Pouring the foundation,
9.15.17 - Pad progress,
7.31.17 - Working on the pond and site grading,
6.28.17 - Site work began mid-June.
5.31.17 - Sitework will soon begin for the first of 10 buildings in a new business park off Clay Road in Katy. This first building will be 12,374 SF (Total) with a 2,708 SF office and 9,666 SF Warehouse.