6.02.22 - Power was turned on today. Flooring and the ceiling tile installation will follow,
3.03.22 - Interior framing is underway,
2.08.22 - Erectors began hanging the steel today,
7/01/21 - This new 8,600 SF office and warehouse is in permitting. Construction updates will be available on this page, so check back for this location's progress and availablility.