twitter facebook linkedin

More than 35 years
of experience in Texas

previous arrow
next arrow
Slider

E Squared Marine

E Squared Marine | 8,000 SF PEMB | Friendswood, TX

Completed project photos,

IMG 8153

IMG 8154

IMG 8172

thumbnail IMG 0229

IMG 8176

IMG 8179

IMG 8182

IMG 8188

IMG 8193

IMG 8196

IMG 8202

IMG 8203

IMG 8208

IMG 8211

IMG 8215

IMG 8220

IMG 8231

IMG 8233

IMG 8242

IMG 8265

IMG 8269

 

 

6.08.20 - Painting is near completion. This project will be completed next week, following landscaping,

17

1

2

5

8

10

12

13

14

18

19

22

 

5.07.20 - Masonry contractors completed the stucco. The wall tile in the restrooms is being installed. M&M Erectors are trimming the building and installing the entry canopy,

95272295 3466569990024474 4243787503628189696 n

95295638 3466570110024462 8884433601769242624 n

95474192 3466570053357801 5326933484940296192 n

95675362 3466570183357788 2841176185482772480 n

95699204 3466570040024469 806365635784212480 n

95709329 3466570120024461 3469914760022065152 n

95775764 3466569980024475 1370859303530921984 n

95840461 3466570193357787 3700212267938217984 n

95857786 3466569786691161 2353273187761913856 n

95876930 3466569653357841 8050737933734379520 n

95903514 3466569880024485 836828296921481216 n

96243266 3466569666691173 2498851469332054016 n

96394352 3466569886691151 8287555408164290560 n

 

4.30.20 - Painters completed their work painting the walls and ceilings. Door frames are being installed. The masonry contractor began the stucco facade,

94767637 3447937445221062 774851119976284160 n

95135831 3447937215221085 7100166202596524032 n

95139936 3447937221887751 4156402837758148608 n

95148798 3447937285221078 6149323643705884672 n

95311911 3447937135221093 263539566944714752 n

95345094 3447937358554404 3414423859867156480 n

95698576 3447937291887744 6088845526311108608 n

95035828 3447937068554433 6895275157108031488 n

 

4.23.20 - The entry canopy is complete. Painters are spraying the exposured structure. Electricians are building the service panels,

13

1

2

3

4

5

6

7

8

9

10

11

12

 

4.14.20 - AVAdek is installing the entry pergola. HVAC ductwork is being installed. Electricians are roughing in the plugs and switches,

93386803 3407481645933309 2434384100413407232 n

93421089 3407481955933278 5939305695756156928 n

93423777 3407482055933268 2872725159813316608 n

93425236 3407482079266599 358783533340164096 n

93426695 3407481979266609 8432734476819234816 n

93429694 3407481669266640 3420630577236148224 n

93473676 3407481849266622 6554092477056286720 n

93482197 3407481739266633 1657674191605858304 n

 

4.02.20 - Interior buildout continues, window and door installation are also underway,

20200401 121708000 iOS

20200401 122405000 iOS

 

3.10.20 - Roof sheeting and siding are underway,

IMG 0051

IMG 0052

IMG 0053

IMG 0054

IMG 0055

IMG 0056

IMG 0057

3.02.20 - Crewmen have finished sheeting the east wall,

IMG 4491

IMG 4492

IMG 4493

IMG 4494

 

2.27.20 - Erectors continue to hang steel, and began sheeting the east wall,

IMG 9845

IMG 9849

 

2.20.20 - The building is delivered and the erectors are shaking out and assembling the steel,

IMG 9654

IMG 9655

2.15.20 - Crews are pouring the foundation,

IMG 0350

IMG 0358

IMG 0360

2.11.20 - Crews are prepping for the foundation pour,

IMG 9636

IMG 9637

 

12.14.19 - Crewmen plan to pour paving on Monday,

E2 12.13

E2 12.13 7

E2 12.13 6

E2 12.13 2

 

12.12.19 - Site work continues,

E2 3

E2 5

E2

 

Crewmen will soon begin constructing a new 8,000 SF office building for E Squared Marine,

exterior thumb

Interior thumb

 

E Squared Marine | 8,000 SF PEMB | Friendswood, TX

3.10.20 - Roof sheeting and siding are underway,

IMG 0051

IMG 0052

IMG 0053

IMG 0054

IMG 0055

IMG 0056

IMG 0057

3.02.20 - Crewmen have finished sheeting the east wall,

IMG 4491

IMG 4492

IMG 4493

IMG 4494

 

2.27.20 - Erectors continue to hang steel, and began sheeting the east wall,

IMG 9845

IMG 9849

 

2.20.20 - The building is delivered and the erectors are shaking out and assembling the steel,

IMG 9654

IMG 9655

2.15.20 - Crews are pouring the foundation,

IMG 0350

IMG 0358

IMG 0360

2.11.20 - Crews are prepping for the foundation pour,

IMG 9636

IMG 9637

 

12.14.19 - Crewmen plan to pour paving on Monday,

E2 12.13

E2 12.13 7

E2 12.13 6

E2 12.13 2

 

12.12.19 - Site work continues,

E2 3

E2 5

E2

 

Crewmen will soon begin constructing a new 8,000 SF office building for E Squared Marine,

exterior thumb

Interior thumb

 

Secor
Hoelscher Weatherstrip Manufacturing Co.

Related Posts

By accepting you will be accessing a service provided by a third-party external to https://northwindsconst.com/