4.08.20 - The facility's signs were installed on Friday. This project was completed.
3.24.20 - The warehouse is being swept. Windows are being cleaned. This project is nearing completion,
3.09.20 - Lights are on. Landscaping and painting are underway. Flooring will soon follow,
2.21.20 - Painters are working on the offices. Cabinets, flooring, and landscaping are being installed,
1.17.20 - Crews are moving along with the interior buildout,
12.30.19 - Erectors are trimming the facility and finishing the canopies. Interior buildout continues with electrical, framing, and drywall,
12.04.19 - Erectors have one final section of roof to sheet. Crewmen continue to build out the interior as site crewmen prepare for the next paving pours,
11.15.19 - Exterior painting is underway and Erectors continue to sheet the roof. HVAC and interior framing is also underway,
10.28.19 - Erectors are sheeting the office side of the facility and will continue to hang roof sections tomorrow. The sprinkler system is being installed and crews are framing for the next paving pour,
10.01.19 - Crewmen are sheeting the roof,
9.13.19 - Crewmen are running the purlin straps, rubbing out the tilt-wall panels, welding the inbeds, and forming for Monday's paving pour,
9.05.19 - The roof system is going up. The truck ramp is poured and Building G's grade beam was poured. The surveyer also began laying out the parking for crewmen to later form,
8.27.19 - Steel is being assembled and erected,
8.20.19 - Crews are lifting the tilt-wall panels,
7.24.19 - Crews continue to prep the site for the next pour,
7.12.19 - Crews began pouring the pad,
7.09.19 - Crews are making up the slab in preparation for Phase 1 of the foundation pour, scheduled for Friday,
6.27.19 - Crewmen are dewatering so they can re-frame the pad,
6.17.19 - Electrical and Plumbing underground are underway. Crews are framing up the pad for the first pour.
6.03.19 - The building pad is 95% complete,
4.29.19 - The storm sewer is complete. The building pad has one lift, with two more to go,
4.09.19 - Crewmen are laying the storm on the North end. The building pad is 90% to start of fill elevation. The fire line and fire hydrant are set and approved by the fire marshall, and the domestic water tap and meter are set,
3.25.19 - Crews have completed the Stom on the South end, with the exception of tying into the downspout drains. Crews have hauled in 26 loads to tighten the SE corner of the building pad. The Storm on the East and NE side of the building is complete,
3.22.19 - Crews continue the mass grading and have laid approximately half of the strom drainage pipe,
3.11.19 - Storm on the south end is complete. Bringing in select fill for pad,
2.27.19 - The brush grinding is complete. The storm on the south end is tied into the street inlet. South storm is 75% complete. Crewmen dug ditches around the building pad area to help release trapped water, and to more quickly dry the areas of saturated soils,
2.16.19 - Crews are installing the storm sewer and dewatering the site,
1.10.19 - Crewmen began clearing trees,
12.27.18 - Silt fencing is installed.
12.17.18 - Excavation is scheduled to begin in January.
2.27.19 - The brush grinding is complete. The storm on the south end is tied into the street inlet. South storm is 75% complete. Crewmen dug ditches around the building pad area to help release trapped water, and to more quickly dry the areas of saturated soils,
2.16.19 - Crews are installing the storm sewer and dewatering the site,
1.10.19 - Crewmen began clearing trees,
12.27.18 - Silt fencing is installed.
12.17.18 - We are very excited to be working again with the Hoelscher family. Our work for them dates back to the 80s when Wayne Robinson added onto their facility that was located in The Heights. We built a new facility for them in 2006 off Houston Oaks Drive, then a second facility at that same location in 2014. Dennis Montesinos oversaw the construction of Hoelscher Weatherstrip's facilities in 2006 and 2014, and will oversee this one as well, as the PM. Doug Grall is the Superintendent. Excavation is scheduled to begin in January.
By accepting you will be accessing a service provided by a third-party external to https://northwindsconst.com/