Hoelscher Weatherstrip Manufacturing Co.

Hoelscher Weatherstrip | 192,000 SF Tiltwall Warehouse and 21,000 SF Office | Tomball, TX

4.08.20 - The facility's signs were installed on Friday. This project was completed.

IMG 5264

 

3.24.20 - The warehouse is being swept. Windows are being cleaned. This project is nearing completion,

IMG 4327

IMG 4164

IMG 4219

IMG 4170

IMG 4177

IMG 4182

IMG 4188

IMG 4208

IMG 4215

IMG 4228

IMG 4231

IMG 4238

IMG 4245

IMG 4252

IMG 4261

IMG 4266

IMG 4273

IMG 4285

IMG 4287

IMG 4306

 

3.09.20 - Lights are on. Landscaping and painting are underway. Flooring will soon follow,

IMG 3709

IMG 3557

IMG 3584

IMG 3605

IMG 3613

IMG 3616

IMG 3641

IMG 3644

IMG 3655

IMG 3673

IMG 3735

IMG 3752

 

2.21.20 - Painters are working on the offices. Cabinets, flooring, and landscaping are being installed,

IMG 9671

IMG 9673

IMG 9674

IMG 9675

IMG 9676

IMG 9677

IMG 9678

IMG 9679

IMG 9680

IMG 9681

IMG 9682

IMG 9683

IMG 9684

IMG 9686

IMG 9687

IMG 9688

IMG 9689

IMG 9690

IMG 9691

IMG 9692

IMG 9693

IMG 9694

IMG 9697

IMG 9698

1.17.20 - Crews are moving along with the interior buildout,

IMG 0595

IMG 0599

IMG 0603

IMG 0605

IMG 0609

IMG 0611

IMG 0612

IMG 0613

IMG 0617

IMG 0619

IMG 0621

IMG 0625

IMG 0627

IMG 0628

IMG 0632

IMG 0632

IMG 0634

IMG 0637

IMG 0639

IMG 0641

IMG 0645

IMG 0646

IMG 0650

IMG 0652

IMG 0654

IMG 0662

IMG 0683

IMG 0691

IMG 0693

 

12.30.19 - Erectors are trimming the facility and finishing the canopies. Interior buildout continues with electrical, framing, and drywall,

IMG 9772

IMG 9777

IMG 9792

IMG 9806

IMG 9810

IMG 9825

IMG 9826

IMG 9829

IMG 9845

 

12.04.19 - Erectors have one final section of roof to sheet. Crewmen continue to build out the interior as site crewmen prepare for the next paving pours,

IMG 7517

IMG 7520

IMG 7522

IMG 7524

IMG 7529

IMG 7533

IMG 7536

IMG 7537

IMG 7538

IMG 7539

IMG 7541

IMG 7542

IMG 7546

IMG 7550IMG 7562

IMG 7566

IMG 7611

 

11.15.19 - Exterior painting is underway and Erectors continue to sheet the roof. HVAC and interior framing is also underway,

IMG 4513

IMG 4516

IMG 4526

IMG 4527

IMG 4530

IMG 4536

10.28.19 - Erectors are sheeting the office side of the facility and will continue to hang roof sections tomorrow. The sprinkler system is being installed and crews are framing for the next paving pour,

IMG 3133

IMG 3142

IMG 3145

IMG 3147

IMG 3150

IMG 3152

IMG 3153

IMG 3159

IMG 3161

IMG 3165

IMG 3183

IMG 3196

 

10.01.19 - Crewmen are sheeting the roof,

IMG 8760

IMG 8761

IMG 8762

IMG 8763

 

9.13.19 - Crewmen are running the purlin straps, rubbing out the tilt-wall panels, welding the inbeds, and forming for Monday's paving pour, 

IMG 5695

IMG 4292

IMG 4312

IMG 4321

IMG 5696

IMG 5697

 

9.05.19 - The roof system is going up. The truck ramp is poured and Building G's grade beam was poured. The surveyer also began laying out the parking for crewmen to later form,

6

1

2

4

7

8

9

9

10

8.27.19 - Steel is being assembled and erected,

IMG 3712

IMG 3713

IMG 3714

IMG 3715

IMG 3716

IMG 3717

 

8.20.19 - Crews are lifting the tilt-wall panels,

IMG 3683

IMG 3693

IMG 3695

 

7.24.19 - Crews continue to prep the site for the next pour,

IMG 3547

IMG 9052

IMG 9060

IMG 9065

IMG 9066

 

7.12.19 - Crews began pouring the pad,

IMG 8147

IMG 8148 thumb

 

7.09.19 - Crews are making up the slab in preparation for Phase 1 of the foundation pour, scheduled for Friday,

IMG 8098

IMG 8088

IMG 8090

IMG 8094

IMG 8096

 

 

6.27.19 - Crewmen are dewatering so they can re-frame the pad,

IMG 7763

IMG 7762

IMG 7736

IMG 7727

 

6.17.19 - Electrical and Plumbing underground are underway. Crews are framing up the pad for the first pour.

3

6

7

 

6.03.19 - The building pad is 95% complete,

1

2

3

4

 

4.29.19 - The storm sewer is complete. The building pad has one lift, with two more to go,

4

7

14

15

16

 

4.09.19 - Crewmen are laying the storm on the North end. The building pad is 90% to start of fill elevation. The fire line and fire hydrant are set and approved by the fire marshall, and the domestic water tap and meter are set,

2

8

7

21

5

6

11

12

3.25.19 - Crews have completed the Stom on the South end, with the exception of tying into the downspout drains. Crews have hauled in  26 loads to tighten the SE corner of the building pad. The Storm on the East and NE side of the building is complete,

5

6

7

8

10

11

 

3.22.19 - Crews continue the mass grading and have laid approximately half of the strom drainage pipe,

IMG 7541

IMG 7542

IMG 7543

IMG 7544

IMG 7545

IMG 7546

IMG 7547

IMG 7548

3.11.19 - Storm on the south end is complete. Bringing in select fill for pad,

1

3

20190311 091142

20190311 091214

20190311 092221

2.27.19 - The brush grinding is complete. The storm on the south end is tied into the street inlet. South storm is 75% complete. Crewmen dug ditches around the building pad area to help release trapped water, and to more quickly dry the areas of saturated soils,

1

2

3

4

5

6

7

8

9

2.16.19 - Crews are installing the storm sewer and dewatering the site,

1

2

3

4

5

6

7

8

9

12

 

1.10.19 - Crewmen began clearing trees,

IMG 7254

IMG 7255

IMG 7257

IMG 7259

 

12.27.18 - Silt fencing is installed.

 

12.17.18 - Excavation is scheduled to begin in January. 

Hoelscher Gray1

Hoelscher Gray3

Hoelsher Gray 02

 

 

 

 

 

 

Hoelscher Weatherstrip | 192,000 SF Tiltwall Warehouse and 21,000 SF Office | Tomball, TX

2.27.19 - The brush grinding is complete. The storm on the south end is tied into the street inlet. South storm is 75% complete. Crewmen dug ditches around the building pad area to help release trapped water, and to more quickly dry the areas of saturated soils,

1

2

3

4

5

6

7

8

9

2.16.19 - Crews are installing the storm sewer and dewatering the site,

1

2

3

4

5

6

7

8

9

12

 

1.10.19 - Crewmen began clearing trees,

IMG 7254

IMG 7255

IMG 7257

IMG 7259

 

12.27.18 - Silt fencing is installed.

 

12.17.18 - We are very excited to be working again with the Hoelscher family. Our work for them dates back to the 80s when Wayne Robinson added onto their facility that was located in The Heights. We built a new facility for them in 2006 off Houston Oaks Drive, then a second facility at that same location in 2014. Dennis Montesinos oversaw the construction of Hoelscher Weatherstrip's facilities in 2006 and 2014, and will oversee this one as well, as the PM. Doug Grall is the Superintendent. Excavation is scheduled to begin in January. 