This facility was purchased by Stillo Construction.
11.01.18 - The building is complete. Parking lot cleaning and striping to follow,
9.12.18 - Masons are installing the cast stone. Grid for the acoustical ceiling is being installed,
8.30.18 - Masonry work is underway as crewmen address HVAC and interior framing,
7.20.18 - Crewmen are installing exterior sheathing and are framing interior walls,
7.16.18 - Crewmen have progressed to roof sheeting,
7.06.18 - Crewmen continue to sheet the walls,
7.03.18 - All steel is hung and crewmen have progressed to sheeting the building,
6.25.18 - Crewmen began hanging steel,
5.01.18 - Paving is poured and sawcut. Crewmen begin seeding the detention pond,
4.26.18 - Crewmen poured the paving this morning,
4.12.18 - Crewmen are setting the storm for Spec Bldg 1. Electricians are trimming out electrical service panel for pond lift station and water well,
3.28.18 - Crewmen poured the foundation this morning,
3.23.18 - Excavation of the detention pond is complete. Slab is made up and ready to pour,
3.13.18 - Progress on the water tank and the detention pond,
1.09.18 - The pad is built for this new facility and crewmen are grading the detention pond. This new office/warehouse is Available for Sale or Lease, off Clay Rd in Katy,
By accepting you will be accessing a service provided by a third-party external to https://northwindsconst.com/