12.15.19 - This property Available for Sale or Lease. Call for more information, 713-671-5300.
12.03.19 - Below are photos of the final interior,
10.05.19 - Landscaping is complete and flooring is near completion,
9.27.19 - Power has been set on the building. Landscaping is being installed. Next week the ceiling tiles and flooring will be installed,
9.13.19 - Flooring and landscape installation are underway,
8.09.19 - Electricians continue to run lights in the warehouse, while plumbers work on the waterline. Painting is underway. M&M Erectors finished trimming out the building,
7.11.19 - Masons are laying the stone. Interior crews are framing the walls. Septic tanks are being installed,
6.28.19 - This office/warehouse is now fully sheeted. Interior framing is underway, as additional crewmen frame for the next paving pours, and the erectors trim the facility,
6.06.19 - Erectors have progressed to installing the wall and skylight sheeting,
3.25.19 - Crews poured the front paving last week,
3.20.19 - Driveway is poured and the pad is complete. Concrete crews will be pouring the front half of the paving tomorrow,