Premier  | 173,982 SF PEMBs and 390,000 SF of Paving | Baytown, TX

This project includes five freestanding buildings and 390,000 SF of paving. There will be a 7,620 SF office building, 76,590 SF tiltwall fab shop, 73,614 SF trailer assembly shop, 11,658 SF paint shop, and a 4,500 SF test station canopy. 

7.28.26 - All tilt-wall panels are lifted for the fab shop. Erectors are cleaning the inbeds and preparing to install the store front for the office building. Erectors also plan to begin hanging purlin rafters in the fab shop. The interior buildout of the office building and trailer shop continue. Crews continue their work on the test and paint stations.

IMG 1797 copy

IMG 1815 copy

IMG 1826 copy

IMG 1847 copy

IMG 1860 copy

IMG 1863 copy

IMG 1865 copy

IMG 1879 copy

IMG 1885 copy

IMG 1886 copy

IMG 1891 copy

IMG 1892 copy

IMG 1900 copy

IMG 1902 copy

IMG 1905 copy

IMG 1906 copy

IMG 1911 copy

IMG 1912 copy

IMG 1915 copy

IMG 1918 copy

IMG 1946 copy

IMG 1955 copy

IMG 1957 copy

IMG 1988 copy

IMG 2017 copy

IMG 2020 copy

IMG 2045 copy

7.25.26 - Crews began hanging tiltwall panels on 7.23 and fill finish today,

default 

default

7.15.26 - All of the foundations are poured, the tiltwall panels are poured, four of the buildings are erected, and 90% of the paving is poured. Crews are working on the interior buildout of the office building and the trailer shop.

6.29.26 - Crews continue to buildout the trailer shop interior. The paint shop is vertical, the office buildout is underway, and the slab is poured for the Fab shop,

default

default

default

6.02.26 - Crews poured tiltwall panels. Warehouse sheeting continues,

default

default

default

default

 

5.16.26 - Crews are pouring another building pad as erectors install the wall sheeting on the first building,

default

default

default

default

default

default

 

4.29.26 - The next pour is underway. Erectors continue to hang the main frame columns and purlin rafters,

Premier4.29.26

default

default

default

default

default

default

 

4.10.26 - The pad for the paint shop, test station, trailer shop, and office are poured,

default

default

default

4.01.26 - Crewmen poured the paint shop pad, the trailer shop pad, the office building pad, the test canopy pad, an additional acre of paving, and a driveway approach. The sitework is complete, and the storm utilities are completed. The first three buildings are arriving mid-April, and the second two in May. 

premier3.25

premier3.25 3

premier3.25 2

 

1.23.26 - We broke ground on this project in mid-November and have 50% of the building pad completed. Crews are moving dirt for paving subgrade and are working on the storm utilities. Our first pour is scheduled in a few weeks.

DCIM\100MEDIA\DJI_0638.JPG

DCIM\100MEDIA\DJI_0630.JPG

DCIM\100MEDIA\DJI_0647.JPG

×
Stay Informed

When you subscribe to the blog, we will send you an e-mail when there are new updates on the site so you wouldn't miss them.

Hoelscher Weatherstrip Expansion
Waller Workforce and Technical Education Complex

About Northwinds Construction

Northwinds Construction is a turnkey general construction company that specializes in design and construction of build-to-suit and development projects. We also offer interior remodeling services, building additions, plan/spec construction, demolition, and sitework.

Quick Links

logo

15400 Vantage Parkway West
Houston, TX 77032

P: 713.671.5300
F: 713.671.5340