Mid-South Control Line

Mid-South Control Line | Building Addition | Houston, TX

10.26.23 - 

10.25.23 - 

9.25.23 - Crews are installing liner panels and are trimming the building,

9.13.23 - Crews are hanging the pre-assembled roof sections,

9.07.23 - The pad is cured and sawcut,

9.02.23 - Crews are pouring the foundation,

8.29.23 - Drilling and pouring piers,

8.14.23 - Setting storm drains,