By KRobinson on Thursday, 12 December 2024
Category: Current Projects

HTeaO

HTeaO | 2,249 SF | Klein, TX

This project includes a 1,109 SF kitchen, a 1,029 SF mercantile, and 112 SF of storage.

12.12.24 - MEP, interior wall, interior ceiling, and Millwork continue. The drives are poured and the drivethrough equipment installation is underway,

11.26.24 - Millwork and MEP work continue. Canopies and the trash gates are installed,

10.25.24 - Electrical and HVAC continue. Crews are taping and floating the interior. Exterior canopy and light installation are underway,

10.16.24 - Interior drywall continues. Additional driveways were poured,

10.10.24 - Electrical and HVAC continue,

10.01.24 - Masonry work is underway. Interior electrical and buildout continues,

9.24.24 - Doors and windows are installed. Electrical is underway,

9.18.24 -

9.04.24 - Crews are framing the building,

8.06.24 - Framing for a  pavement pour,

8.02.24 - Crewmen are pouring the building foundation this morning,

6.04.24 - Storm and utility work continue,

5.10.24 - Storm and utility work are underway,

4.17.24 - Sitework continues,

4.02.24 - Crews are excavating and clearing the site,