By KRobinson on Monday, 18 August 2025
Category: Current Projects

The Word of God Christian Fellowship Church Phase II

The Word of God Christian Fellowship Church Phase II | Building Addition, Remodel, and Paving | Cypress, Texas

8.18.25 - Walls are framed and crews have sheetrocked the sanctuary. The building foundation has been poured for the addition and the detention pond is complete. Additional paving for parking will be poured in October.

 8.05.25 - The foundation for the expansion was poured last weekend. The steel will be delivered soon. Framing crews are working on framing the sanctuary expansion. Dirt crews are excavating the new detention pond.

Related Posts