By Kimber Robinson on Thursday, 04 December 2025
Category: Current Projects

Waller Workforce and Technical Education Complex

Waller Workforce and Technical Education Complex | 17,930 SF | Waller, TX

12.05.25 - Erectors continue to install the metal panels. They will have the building fully sheeted and insulated within the next few weeks. A concrete crew will be on site next week to pour half of the parking lot,

11.14.25 - Erectors are hanging the steel,

10.31.25  - Crews are pouring the building foundation,

10.23.25 - The piers are poured and underground utilities are going in. Form boards are up and crews plan to pour next week.

10.09.25 - The site crew is installing the storm sewer and utilities. Concrete crews should begin drilling piers this week,

9.23.25 - Our crews just completed construction of the foundation pad. Our next step is to drill and pour the foundation piers, then proceed to forming and pouring the foundation.

9.15.25 - We are excited to be constructing Blinn College District’s new Waller Workforce and Technical Education Complex. Crews have broken ground and photos of this project’s progression will be available on this page.

Blinn College District announces new Waller Workforce and Technical Education Complex
Source: Brenham Banner-Press

https://share.google/A04SYPG6PgHQRAkzj