By KRobinson on Thursday, 02 June 2022
Category: Current Projects

20213 Binford Rd

20213 Binford Rd | 20,000 SF Trade School | Waller, TX

6.02.22 - Crewmen are addressing punch out items and the project will be completed by next week,

5.11.22 - This project is complete. Waiting on power,

3.18.22 - The stucco is complete. The ceiling grid installation is underway, and the electricians are installing the lights,

3.02.22 - Crews have made great progress this month. The paving is complete and masonry has begun. Interior crews continue to hang sheetrock,

2.15.22 - Interior crews are hanging drywall and the concrete crewmen are forming the paving. The excavation of the business park's eastern retention pond is almost complete,

1.19.22 - Erectors are sheeting the roof. Framers are framing the walls.

1.04.22 - Erectors are hanging steel for this new facility,

12.16.21 - Crews are preparing for the foundation pour,

11.11.21 - Site work is underway for a new 20,000 SF trade school, located at 20213 Binford Rd,