Secor Phase 2 | 45,000 SF PEMB and 5,500 SF Office Space Renovations | Houston, TX

9.30.25 - Erectors began hanging the main frame columns,

default

default

 

9.24.25 - The foundation and additional paving has cured. Crews will soon shake out the steel and begin erecting the building,

default

default

9.17.25 - Crews poured the foundation on Friday. The building will go vertical next week.

SecorPhase2 9.17