Secor Phase 2 | 45,000 SF PEMB and 5,500 SF Office Space Renovations | Houston, TX

11.14.25 - Erectors are siding the office and are completing the installation of the skylight panels,

default

secorphase2 11.11.25 2

secorphase2 11.13.25 2

secorphase2 11.13.25

10.14.25 - Erectors continue to assemble and erect the purlin rafters, 

default

default

SecorPhaseII 10.14 2

9.30.25 - Erectors began hanging the main frame columns,

default

default

 

9.24.25 - The foundation and additional paving has cured. Crews will soon shake out the steel and begin erecting the building,

default

default

9.17.25 - Crews poured the foundation on Friday. The building will go vertical next week.

SecorPhase2 9.17