Secor Phase 2 | 45,000 SF PEMB and 5,500 SF Office Space Renovations | Houston, TX

4.01.26 - Erectors installed the accent trim to the new, and existing facilities. The entrance is also painted,

default

secorphase2 3.31 2

default

secorphase2 3.31 4

default

default

 

3.16.26 - The parking areas are striped,

default

SecorPhaseII 3.16.26 2

2.22.26- Crews have 80% of the paving completed. Crews are wrapping up the interior with a completion date set for early April,

default

default

secorphase2 feb

secorphase2 feb6

secorphase2 feb7

1.27.26 - The interior buildout continues with a completion date set for late March,

Jan27

Jan27 2

Jan27 4

Jan27 3

 

1.23.26 - Recent pours are curing and erectors are trimming the exterior,

default

default

Jan23 4

default

 

1.15.26 - Amazing bends in conduit and custom racks for distribution panels,

20260115 112924 copy

20260115 112931 copy

20260115 113024 copy

 

1.02.26 - The building is erected. The interior buildout is 40% complete. Crewmen have completed 70% of the paving. All storm utilities are done, and we expect a late March completion date.

1749 1.02.26

1749 1.02.26 2

1749 1.02.26 3

 

11.14.25 - Erectors are siding the office and are completing the installation of the skylight panels,

default

secorphase2 11.11.25 2

secorphase2 11.13.25 2

secorphase2 11.13.25

10.14.25 - Erectors continue to assemble and erect the purlin rafters, 

default

default

SecorPhaseII 10.14 2

9.30.25 - Erectors began hanging the main frame columns,

default

default

 

9.24.25 - The foundation and additional paving has cured. Crews will soon shake out the steel and begin erecting the building,

default

default

9.17.25 - Crews poured the foundation on Friday. The building will go vertical next week.

SecorPhase2 9.17