Hoelscher Weatherstrip MFG, Co.  | 48,000 SF Building Expansion | Tomball, TX

5.14.26 - Crews are hanging the last of the tilt-wall panels. Erectors are also hanging steel,

HoelscherExpansion5.07.26

HoelscherExpansion5.07.26 3

HoelscherExpansion5.07.26 2

 

4.22.26 - Crews began hanging tilt-wall panels on 4.18. There are four more panels to hang.

Hoelscher4.18

Hoelscher4.21

4.08.26 - Crews are pouring the tilt-wall panels,

Hoelscher4.08

4.01.26 - Crews are forming for the tilt-wall panels.  

HoelscherExpansion3.31

HoelscherExpansion3.31 2

 

3.18.26 - Crewmen poured the slab this morning for the building expansion,

Hoelscher3.18.26

Hoelscher3.18.26 2

3.17.26 - Crews continue preparing the pad for the foundation pour,

Hoelscher3.17.26

3.05.26 - Crewmen are pouring the piers,

Hoelscher3.5.26