Engineered Air Balance  | 60,000 SF Corporate Offices and Training Center | Spring, TX

9.10.26 - Crews are drilling and pouring piers for the building foundation. Crews are forming for the first paving pour, scheduled for tomorrow. Crews have also drilled and set 25 Geothermal wells for their Geothermal system,

default

default

EAB9.10.26 3

EAB9.10.26 7

EAB9.10.26 4

EAB9.10.26 5

EAB9.10.26 6

8.03.26 - Sitework is underway,