Wilson Air | 28,000 SF Additional Airplane Hangar and Office | Houston, TX
1.21.19 - Crewmen are installing insulaton straps. Plumbers continue to relocate plumbing lines and the interior build out continues,
1.07.19 - Hanging rafters,
1.21.19 - Crewmen are installing insulaton straps. Plumbers continue to relocate plumbing lines and the interior build out continues,
1.07.19 - Hanging rafters,
1.10.19 - LED lights are in and display slatwall is in. Crewmen will next address the ceiling tile and paint.
1.09.19 - Crewmen began their work on this project last Monday. Crewmen are to replace the ceiling, install slatwall for inventory displays, install new LED 2x4 lights, repaint, replace electrical devices and receptacles, repair and refinish the sales counter, and replace sales doors to warehouse doors,
6.28.18 - Crewmen are installing a storm system, approximately 600 feet of storm pipe and a detention Pond. Trevor Robinson is the PM and Austin Leitko is the Superintendent,