twitter facebook linkedin

smartslider3[2]

Northwinds Construction

View important updates by Northwinds Construction

Wilson Air

Wilson Air | 28,000 SF Additional Airplane Hangar and Office | Houston, TX

10.15.19 - This project is complete for now. The office area will later be completed per tenant's request,

IMG 9243

IMG 9242

IMG 9240

IMG 9236

IMG 9223

IMG 9222

IMG 9220

IMG 9218

IMG 9206

IMG 9186

IMG 9147

IMG 9074

IMG 9028

IMG 9029

IMG 9036

IMG 9037

IMG 9038

IMG 9130

IMG 9138

IMG 9046

IMG 9050

IMG 9069

IMG 9073

IMG 9102

IMG 9108

IMG 9105

IMG 9117

IMG 9099

IMG 9119

IMG 9126

IMG 9085

 

9.05.19 - This project is near completion. Tilt installation is underway then punch-out items will be addressed,

IMG 8504

IMG 8505

IMG 8506

IMG 8508

IMG 8509

IMG 8510

IMG 8511

 

9.03.19 - Crews are painting the breakroom, restrooms, and doors. Lights were installed in the restrooms. M&M Erectors separated hanger doors 3 & 4, then repaired the weatherstrip after the separation,

1

2

5

10

13

14

15

16

20

31

32

 

8.16.19 - Electricians are working on the rolling hangar doors to prep for power. Flooring contractors began work by demoing existing tile in the women's room and by installing wall tiles in the men's room,

3

1

4

2

 

6.03.19 - Electricians are running extra grounding and cad welding to the columns,

9

4

5

8

 

4.29.19 -  Electricians are installing exterior wall lights on the North side of the hangar. Crews continue to paint steel and conduit in the hangar areas. Crewmen are also breaking up the driveway, while A/C work continues in the offices, and blades are being installed on the big fan,

1

3

4

10

14

16

17

22

 

4.24.19 - The doors are complete. Electrical and interior painting continues. This project is near completion,

IMG 3916

IMG 3870

IMG 3880

IMG 3899

4.01.19 - Crewmen continue to trim and sheet the rolling doors, and line the interior hanger walls. Electrical continues as well as interior painting,

IMG 7585

IMG 7588

IMG 7590

IMG 7592

IMG 7593

IMG 7596

3.29.19 - Liner panels are being installed,

IMG 1035

IMG 1036

IMG 1037IMG 1038IMG 1040

3.17.19 - Crewmen poured the door railings and continue to sheet the high roof with insulated roof sheeting. Crewmen are also installing the gutters and downspouts o the west side. Electricians continue hangers and conduit for the high bay lights as interior hangar walls are bing insulated and the gas line is being run in the hangar,

19

23

27

3.11.19 - Crewmen have progressed to sheeting the highest roof and installing the gutters and downspouts. Electrical work continues,

IMG 0870

IMG 0871

IMG 0872

IMG 0873

IMG 0874

IMG 0875

 

2.20.19 - Crewmen continue to sheet the lower roof. Electricians are roughing in the electrical and interior duct work is also underway,

IMG 2718

IMG 2719

IMG 2720

IMG 2721

 

1.21.19 - Crewmen are installing insulaton straps. Plumbers continue to relocate plumbing lines and the interior build out continues,

IMG 0354

IMG 0355

IMG 0356

IMG 0357

1.07.19 - Hanging rafters,

IMG 2601

IMG 2603

 

12.18.18 - Crews began hanging steel last week,

IMG 0055

IMG 0056

IMG 0057

 

 

12.03.18 - The foundation has been saw cut,

IMG 3400

11.29.18 - The foundation was poured this week,

 IMG 0197

IMG 0205

IMG 0717

 

11.19.18 - Crewmen are tying double rebar mat for the foundation,

3

4

5

 

10.21.18 - Crewmen  have drilled 27 of the 32 piers,

13

1

10

14

9.24.18 - Crews are building pad for the foundation,

3

5

6

 

9.07.18 - Site excavation continues,

4

1

2

3

 

8.15.18 - Work began for Wilson Air's new 28,000 SF hangar and office, which is to tie into the hangar we constructed in 2014. Crewmen began breaking up the outside perimeter of slab,

IMG 6308

A

B

6

 

  5403 Hits
5403 Hits

Contact Us

Please let us know your name.
Invalid Input
Invalid Input
Please let us know your email address.
Please let us know your message.